Decided: approved on 3 Mar 2011Mixed use

Where it is in the process

Approved on 3 Mar 2011

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination3 Mar 2011 (done)
  8. Approved3 Mar 2011

What it proposes

The portal gives no description.

Modifications

14 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 6MP10_0048-Mod6

Withdrawn: withdrawn

Its 2 documents

2 documents in 2 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

Agency Submissions1

See the document on the Planning Portal

Its page on the Planning Portal

Mod 1MP10_0048-Mod1

Withdrawn: withdrawn

Its 2 documents

2 documents in 2 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

EIS1

See the document on the Planning Portal

Its page on the Planning Portal

Barangaroo - Headland Park MOD 14 - Condition D15MP10_0048-Mod-14

Decided: approved on 3 Jul 2025 by the department (executive director)

Modify condition D15 to extend the time period to install the interpretive structure from 30 September 2025 to 1 April 2027

Its 6 documents

6 documents in 4 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Barangaroo - Headland Park MOD 13 - HCT TimingMP10_0048-Mod-13

Decided: approved on 21 Nov 2023 by the department (executive director)

Extend the timeframe for submission of the final design documents for the interpretative structure of the Harbour Control Tower and installation of the interpretative structure.

Its 8 documents

8 documents in 4 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Agency Advice3

See the 3 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Barangaroo - Headland Park MOD 12 - Control TowerMP10_0048-Mod-12

Decided: approved on 24 Sep 2020 by the department (director)

The proposal seeks to modify: Condition B43 to extend the period to submit the final design documents to 30 June 2023Condition D15 to extend the completion date for the installation to 30 September 2024

Its 3 documents

3 documents in 2 folders, each on the NSW Planning Portal

Agency Advice1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Barangaroo - Headland Park MOD 11 - Headland ParkMP10_0048-Mod-11

Decided: approved on 12 Dec 2019 by the department (director)

Modification to Conditions:-B43 to extend the period to submit the final design documents for the physical interpretive device to 30/06/2020-D15 to extend the completion date for the installation of the physical interpretive device to 30/06/2021

Its 5 documents

5 documents in 4 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice1

See the document on the Planning Portal

Additional Information1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Barangaroo - Headland Park MOD10 - Harbour TowerMP10_0048-Mod10

Decided: approved on 13 Oct 2017 by the department (director)

/

Its 4 documents

4 documents in 2 folders, each on the NSW Planning Portal

Application2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Barangaroo - Headland Park MOD9 - LandscapingMP10_0048-Mod9

Decided: approved on 10 Nov 2016 by the department (director)

/

Its 13 documents

13 documents in 5 folders, each on the NSW Planning Portal

Application4

See the 4 documents on the Planning Portal

Submissions1

See the document on the Planning Portal

Agency Submissions1

See the document on the Planning Portal

Response to Submissions5

See the 5 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Barangaroo - Headland Park MOD8 - DemoilitionMP10_0048-Mod8

Decided: approved on 6 May 2016 by the department (director)

/

Its 22 documents

Its page on the Planning Portal

Barangaroo - Headland Park MOD7 - Demo TimingMP10_0048-Mod7

Decided: approved on 27 Nov 2015 by the department (director)

/

Its 7 documents

7 documents in 4 folders, each on the NSW Planning Portal

Application3

See the 3 documents on the Planning Portal

Submissions1

See the document on the Planning Portal

Agency Submissions1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Barangaroo - Headland Park MOD4 - Tower DemoMP10_0048-Mod4

Decided: approved on 30 Jul 2015 by the Minister

/

Its 50 documents

Its page on the Planning Portal

Barangaroo - Headland Park MOD5 - Plaza & WalkwayMP10_0048-Mod5

Decided: approved on 16 Jul 2014 by the department (executive director)

/

Its 9 documents

9 documents in 2 folders, each on the NSW Planning Portal

EIS7

See the 7 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 3MP10_0048-Mod3

Decided: approved with conditions on 9 May 2013 by the department (executive director)

Its 8 documents

8 documents in 4 folders, each on the NSW Planning Portal

EIS2

See the 2 documents on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Recommendation2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 2MP10_0048-Mod2

Decided: approved on 17 Apr 2012 by the department (deputy director-general)

Its 4 documents

4 documents in 2 folders, each on the NSW Planning Portal

Application2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.