Baldon Wind Farm
A wind farm of up to 175 turbines near Moulamein
Where it is in the process
Approved on 10 Nov 2026
What it proposes
AI summary. Written from this project's page and its Development Consent and Assessment Report - Recommendation to IPC on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A wind farm of up to 175 turbines near Moulamein
The project is a wind farm in the South West Renewable Energy Zone, about 13 km north of Moulamein, mainly in the Murray River Council area and partly in Hay Shire. The department's report describes up to 175 turbines in two stages: 46 in Stage 1 and 129 in Stage 2. It also includes a battery and substations. The consent caps the battery at 200 MW and 400 MWh and the turbines at 300 m tall. The project has up to 400 construction jobs and 35 operation jobs.
The environmental impact statement (EIS) drew 80 submissions: 72 objecting, 2 supporting and 6 commenting. The proponent amended the project and removed five turbines. The department's assessment report went to the Independent Planning Commission without an overall recommendation. The Commission approved the project on 10 Nov 2026, with conditions. Next, the proponent must meet those conditions, including a voluntary planning agreement with the councils, before construction.
- Maximum wind turbines approved
- 175 turbinesDevelopment Consent
- Stage 1 turbines
- 46 turbinesAssessment Report - Recommendation to IPC
- Stage 2 turbines
- 129 turbinesAssessment Report - Recommendation to IPC
- Maximum turbine height
- 300 mDevelopment Consent
- Maximum battery power
- 200 MWDevelopment Consent
- Maximum battery storage
- 400 MWhDevelopment Consent
- Construction jobs
- 400 jobsAssessment Report - Recommendation to IPC
- Operation jobs
- 35 jobsAssessment Report - Recommendation to IPC
The department's description
Construction and operation of a wind farm with up to 180 wind turbines, battery storage and associated infrastructure.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
80 submissions: 68 from the public, 9 from organisations and 3 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
100 documents in 10 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs5
SEARs21
- Issued SEARs
- SEARs Advice - BCS
- SEARs Advice - CASA
- SEARs Advice - Crown Lands
- SEARs Advice - DPE Water Advice
- SEARs Advice - DPI Agriculture
- SEARs Advice - DPI Fisheries
- SEARs Advice - DPIRD Resources
- SEARs Advice - Defence Advice
- SEARs Advice - EPA
- SEARs Advice - Edward River Council
- SEARs Advice - FRNSW
- SEARs Advice - HNSW ACH
- SEARs Advice - Hay Shire Council
- SEARs Advice - Heritage Council NSW
- SEARs Advice - Murray River Council
- SEARs Advice - RFS
- SEARs Advice - Telco
- SEARs Advice - TfNSW
- SEARs Advice - WaterNSW
- Supplementary SEARs - MNES
EIS16
- Appendix F1 Vol 1 BDAR
- Appendix F1 Vol 2 BDAR Appendices A to K
- Appendix F1 Vol 3 BDAR Appendix L [L.7_L.12]
- Appendix F1 Vol 3 BDAR Appendix [L.1_L.6]
- Appendix F10 EMI and EMF
- Appendix F11 Blade Throw
- Appendix F2 ACHAR_Public version
- Appendix F3 LVIA
- Appendix F4 SIA
- Appendix F5 Traffic
- Appendix F6 NVIA
- Appendix F7 Soil and Agriculture
- Appendix F8 PHA
- Appendix F9 Aviation
- Application Form
- EIS
Response to Submissions14
- Request RTS Letter
- Submission Report - App F.1 (Pt 2) - Archaeological Technical Report
- Submissions Report
- Submissions Report - App E - BDAR
- Submissions Report - App E - BDAR App L to M_part 1
- Submissions Report - App E - BDAR App L to M_part 2
- Submissions Report - App E - BDAR Appendices A - K
- Submissions Report - App E.2 - Biodiversity Offset Strategy
- Submissions Report - App F.1 (Pt 1) - Revised ACHAR
- Submissions Report - App F.2 - Addendum ACHAR Road Upgrades
- Submissions Report - App G - Flood study
- Submissions Report - App H - Updated OSOM Route Study
- Submissions Report - App I – Updated Traffic Impact Assessment
- Submissions Report - App K – Aviation Obstacle Lighting Plan
Agency Advice17
- EIS Advice - BCS
- EIS Advice - CASA
- EIS Advice - Crown Lands
- EIS Advice - DCCEEW Water
- EIS Advice - DPI Agriculture
- EIS Advice - DPI Fisheries
- EIS Advice - DoD
- EIS Advice - EPA
- EIS Advice - Edward River Council
- EIS Advice - FRNSW
- EIS Advice - Heritage NSW
- EIS Advice - MEG
- EIS Advice - NPWS
- EIS Advice - NSW RFS
- EIS Advice - TfNSW
- EIS Advice - WaterNSW
- IEAPET advice
Additional Information17
- Request for Information 1 (22 May 2025)
- Request for Information 2 (September 2025)
- Request for Information 3 (October 2025)
- Response to RFI 1 (SEP 2025) BDAR Appendices A - K
- Response to RFI 1 (SEP 2025) BDAR Appendices L to M
- Response to RFI 1 (SEP 2025) BDAR V2.1 Cover Letter
- Response to RFI 1 (SEP 2025) DPHI RFI Response Cover Letter
- Response to RFI 1 (SEP 2025) Groundwater Impact Assessment
- Response to RFI 1 (SEP 2025) Independent SAII evaluation letter
- Response to RFI 1 (SEP 2025) Noise and vibration assessment – Market St and Sturt Hwy
- Response to RFI 1 (SEP 2025) Noise and vibration assessment – Murray Valley Hwy and Sturt Hwy
- Response to RFI 1 (SEP 2025) Plains-Wanderer Management Plan
- Response to RFI 1 (SEP 2025) Preliminary Site Investigation for Contamination
- Response to RFI 1 (SEP 2025) Revised BDAR V2.1
- Response to RFI 1 (SEP 2025) Revised Traffic Impact Assessment
- Response to RFI 2 (Nov 2025) - Revised TIA
- Response to RFI 2 (Oct 2025) - TfNSW comments
Recommendation5
Determination2
What's near it
Where it is
- Suburb
- Keri Keri
- Council areas
- Murray River, Hay, Edward River
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.