Austen Quarry

Austen Quarry extension, Jenolan Caves Road, Hartley

Decided: approved on 15 Jul 2015QuarriesNeighbourhood scale

Where it is in the process

Approved on 15 Jul 2015

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination15 Jul 2015 (done)
  9. Approved15 Jul 2015

What it proposes

AI summary. Written from this project's page and its 2. Austen Quarry Extension - Development Consent.pdf on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

Austen Quarry extension, Jenolan Caves Road, Hartley

The project extends the existing Austen Quarry at 391 Jenolan Caves Road, Hartley, in the Lithgow City Council area, as the Austen Quarry Stage 2 Extension Project. Quarrying may continue until 30 June 2050. The consent limits transport to 1.1 million tonnes of quarry products in a financial year and 250 laden trucks leaving on any one day. No capital investment or job numbers are stated.

The environmental impact statement (EIS) is dated October 2014, and the proponent responded to submissions in January 2015. The project drew 3 submissions: 2 objecting and 1 supporting. The department's Executive Director approved it on 15 Jul 2015, with conditions on noise, blasting, air quality, water and transport. Next, the proponent must prepare management plans before quarrying under the new consent begins, surrender its earlier consent and enter a planning agreement with the council.

Maximum annual product transport
1,100,000 tonnes a year2. Austen Quarry Extension - Development Consent.pdf
Maximum laden trucks a day
250 trucks2. Austen Quarry Extension - Development Consent.pdf
Average laden trucks a day (monthly limit)
150 trucks2. Austen Quarry Extension - Development Consent.pdf
Public submissions
3 submissionsPortal page

The portal gives no description.

Submissions

What the public, organisations and public authorities said, counted by where they stood.

3 submissions: 2 from the public and 1 from organisations

Object2
Support1
Comment0

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

4 changes to the project after its decision, each assessed as a case of its own, newest first.

Austen Quarry Modification 4SSD-6084-Mod-4

Under way: at prepare mod report

Use of a secondary haulage route for use during emergencies or unforeseen circumstances combined with an extension of the loading and dispatch hours to permit these activities 24 hours Monday to Friday. Refer to the attached scoping report.

Its page on the Planning Portal

Austen Quarry (MOD 3) - Biodiversity offsettingSSD-6084-Mod-3

Under way: at response to submissions · 1 submission

Amending approved biodiversity offsetting arrangements and staging arrangements

Its 13 documents

Its page on the Planning Portal

Austen Quarry MOD 2 - Overburden EmplacementSSD-6084-Mod-2

Decided: approved on 15 Jul 2019 by the department (director)

Proposal to modify the boundary of overburden emplacement

Its 18 documents

Its page on the Planning Portal

Austen Quarry Extension MOD 1 - Dispatch LimitsSSD-6084-MOD-1

Decided: approved on 15 Aug 2018 by the department (director) · 2 submissions

/

Its 31 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

79 documents in 13 folders, each on the NSW Planning Portal

Request for DGRS1
Application2
DGRs2
EIS33
Agency Submissions9
Response to Submissions1
Recommendation1
Determination2
Management Plans and Strategies1
Agreements8
Reports9
Independent Reviews and Audits3
Other Documents7