Atlassian - Office and Hotel Development

Decided: approved on 15 Oct 2021Tourism and recreation

Where it is in the process

Approved on 15 Oct 2021

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination15 Oct 2021 (done)
  9. Approved15 Oct 2021

What it proposes

The department's description

Office and Hotel Tower and Adaptive Reuse of the Former Inwards Parcel Sheds

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

22 submissions: 7 from the public, 2 from organisations and 13 from public authorities

Object6
Support2
Comment14

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

15 changes to the project after its decision, each assessed as a case of its own, newest first.

Atlassian Central Modification 15SSD-10405-Mod-15

Withdrawn: withdrawn

Minor amendments to the approved stratum subdivision, including changing the subdivision layout from four (4) lots to five (5) lots.

Its page on the Planning Portal

SSD - 10405 - Modification 12SSD-10405-Mod-12

Withdrawn: withdrawn

Minor internal layout adjustments, realignment of facade, removal of planter box and modification to Condition G49.

Its page on the Planning Portal

Atlassian Headquarters MOD 14 - Modification to SubdivisionSSD-10405-Mod-14

Decided: approved on 9 Oct 2026 by the department (team leader)

Modification to Subdivision

Its 10 documents

Its page on the Planning Portal

Atlassian Headquarters MOD 13SSD-10405-Mod-13

Decided: approved on 24 Aug 2026 by the department (team leader)

Minor internal amendments, removal of a planter box and modification to the northern elevation at ground level.

Its 12 documents

Its page on the Planning Portal

Atlassian Headquaters MOD 11 - Event SpaceSSD-10405-Mod-11

Decided: approved on 28 Oct 2025 by the department (team leader)

Alterations to the crown event space and stairs on levels 35, 37 and 38 of the Atlassian tower, Lee Street, Haymarket, approved on 28 Oct 2025.

The department's description

Alterations to the crown event space and stairs on levels 35, 37 and 38

Its 12 documents

Its page on the Planning Portal

Atlassian Headquaters MOD 10 - Construction HoursSSD-10405-Mod-10

Decided: approved on 8 Oct 2025 by the department (team leader)

Minor amendments to construction hours to allow for internal fitout works and design amendments to building light, landscape planters and cupboard doors.

Its 20 documents

Its page on the Planning Portal

Atlassian Headquarters MOD 9 - Alterations to CrownSSD-10405-Mod-9

Decided: approved on 29 Jan 2025 by the department (team leader)

Minor internal and external alterations to tower crown levels, including introduction of event use

Its 17 documents

Its page on the Planning Portal

Atlassian Headquarters MOD 8 - Tower CoreSSD-10405-Mod-8

Decided: approved on 25 Oct 2024 by the department (team leader)

Amendments to the materiality of the megacolumns, tower core and tower level 1 soffit design and reinstate upper ground level retail tenancy removed in previous modification.

Its 22 documents

Its page on the Planning Portal

Atlassian Headquarters MOD 7 - Shed Roof and StairsSSD-10405-Mod-7

Decided: approved on 25 Oct 2024 by the department (team leader)

Redesign of Inwards Parcel Shed roof and southern stair, amendments to the OSD pavilion and landscaping and tower façade and internal amendment to Basement to OSD level and YHA levels

Its 31 documents

Its page on the Planning Portal

Atlassian Headquarters MOD 6 - Retail ChangesSSD-10405-Mod-6

Decided: approved on 2 Nov 2023 by the department (team leader)

- Deletion of the Adina goods lift and add a new retail goods lift - Combine retail tenancies at lower ground level - Minor changes to gross floor area - Changes to public art conditions

Its 20 documents

Its page on the Planning Portal

Atlassian Headquarters MOD 5 - Design AmendmentsSSD-10405-Mod-5

Decided: approved on 9 Jun 2023 by the department (team leader)

Design amendments to the YHA bedrooms, tower crown levels and Ambulance Avenue Wall arches.

Its 18 documents

Its page on the Planning Portal

Atlassian Headquarters MOD 4 - Design AmendmentsSSD-10405-Mod-4

Decided: approved on 14 Apr 2023 by the department (team leader)

Minor modifications to basement level 1, YHA lobby level, upper link zone skylights, DDA access lift within the public domain, and materiality of jack arches within the lower ground link zone.

Its 21 documents

Its page on the Planning Portal

Atlassian Headquarters MOD 3 - Tower DesignSSD-10405-Mod-3

Decided: approved on 12 Dec 2022 by the department (team leader)

Design changes including restacking of the tower structure, habitat design changes, facade modifications, and increasing the GFA.

Its 23 documents

Its page on the Planning Portal

Atlassian Headquarters MOD 2 - Design ChangesSSD-10405-Mod-2

Decided: approved on 9 Dec 2022 by the department (team leader) · 2 submissions

Minor design changes, changes to respite periods and amendment to construction staging and the timing of construction certificates.

Its 31 documents

Its page on the Planning Portal

Atlassian Headquarters MOD 1 - Design ChangesSSD-10405-Mod-1

Decided: approved on 17 Aug 2022 by the department (team leader)

A minor modification to the basement retaining wall design, amendment to the definition of construction/building works and administrative amendments to various Conditions in Section C and Part E.

Its 14 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

216 documents in 16 folders, each on the NSW Planning Portal

Early Consultation1
Notice of Exhibition1
Request for SEARs2
SEARs2
EIS40
Response to Submissions24
Agency Advice27
Amendments1
Additional Information7
Determination12
Post-determination Notices1
Management Plans and Strategies39
Reports7
Independent Reviews and Audits1
Notifications1
Other Documents50

What's near it