Approved

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination (done)
  10. Approved

What it proposes

The portal gives no description.

Modifications

7 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 5 - The ArgyleDA174-07-2005-Mod-5

Decided: approved by the department (director)

Its page on the Planning Portal

Mod 4 - The ArgyleDA174-07-2005-Mod-4

Decided: approved by the department (director)

Its page on the Planning Portal

Mod 3 - The ArgyleDA174-07-2005-Mod-3

Decided: approved by the department (director)

Its page on the Planning Portal

Mod 2 - The ArgyleDA174-07-2005-Mod-2

Decided: approved by the department (director)

Its page on the Planning Portal

Mod 1 - The ArgyleDA174-07-2005-Mod-1

Decided: approved by the department (director)

Its page on the Planning Portal

Mod 7 - The ArgyleDA174-07-2005-Mod-7

Decided: approved on 23 Nov 2011 by the department (director)

Its 9 documents

9 documents in 3 folders, each on the NSW Planning Portal

Application4

See the 4 documents on the Planning Portal

Submissions3

See the 3 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.