On the map
Part 3A project

Apex Gas

Decided: approved on 23 Sep 2009Energy: other

Where it is in the process

Approved on 23 Sep 2009

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination23 Sep 2009 (done)
  10. Approved23 Sep 2009

What it proposes

The portal gives no description.

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 2 - Extension of TimeMP07_0103-Mod-2

Decided: refused on 10 Jul 2013 by the Independent Planning Commission · 232 submissions

Its 158 documents

Its page on the Planning Portal

Mod 1 - Additional BoreholeMP07_0103-Mod-1

Decided: approved on 21 Nov 2011 by the Independent Planning Commission

Its 64 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

26 documents in 8 folders, each on the NSW Planning Portal

Request for DGRS1
Application1
EA3
Submissions6
Agency Submissions8
Response to Submissions5
Recommendation1
Determination1

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.