242-244 Beecroft Road,Epping
Concept plan for apartments at 242-244 Beecroft Road, Epping
Where it is in the process
Approved on 22 Jul 2020
What it proposes
AI summary. Written from this project's page and its Assessment Report - Epping SSD 8784 - Part 1 and Development Consent - Epping SSD 8784 on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
Concept plan for apartments at 242-244 Beecroft Road, Epping
This State significant development is a Stage 1 concept application for a residential flat building development at 242-244 Beecroft Road, Epping, in the City of Parramatta council area. A concept application sets the broad shape of a development, and each later stage needs its own approval. No number of homes, building height or capital investment is stated. The portal lists it under rail transport facilities.
The environmental impact statement was exhibited and drew 70 submissions: 61 objecting and 9 commenting. The proponent responded to the submissions and gave the department further information. The Minister approved the concept application on 22 Jul 2020, with conditions. Next, detailed designs must be lodged and assessed in later applications that follow the consent.
- Public submissions
- 70 submissionsPortal page
- Submissions objecting
- 61 submissionsPortal page
The department's description
Stage 1 Concept Application for a residential flat building development.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
70 submissions: 62 from the public, 1 from organisations and 7 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Modifications
1 change to the project after its decision, each assessed as a case of its own, newest first.
242-244 Beecroft Road , Epping - MOD 1SSD-8784-Mod-1
Modification 1 Modified Building Envelopes
Its 24 documents
24 documents in 6 folders, each on the NSW Planning Portal
Notice of Exhibition1
Modification Application4
Response to Submissions8
- Appendix 1 Revised Architectural Plans May 2023
- Appendix 2 Revised Landscaping Plans
- Appendix 3 DPE Response
- Appendix 3A Supplementary DPE Response May 2023
- Appendix 3B State Design Review Panel Response
- Appendix 4, Revised Landscape Design Report
- Request RTS - Concept MOD 242-244 Beecroft Road, Epping
- Response To Submissions Report (Mod)
Agency Advice6
Recommendation2
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
69 documents in 7 folders, each on the NSW Planning Portal
SEARs5
EIS25
- Appendix A. Secretarys Environmental Assessment Requirement
- Appendix A. Secretarys Environmental Assessment Requirement
- Appendix B. Biodiversity Development Assessment Report Waiv
- Appendix C. Capital Investment Value Report_SSD-8784
- Appendix D. Final Plan of Subdivision - Lot 220_ DP 1251471
- Appendix E. Design Plans (July 2019)
- Appendix E. Design Report (July 2019)
- Appendix F. Design Excellence Strategy Report (July 2019)
- Appendix G. Stakeholder Engagement Outcomes Report
- Appendix H. Visual Impact Assessment Report - updated site
- Appendix I. Traffic and Transport Study
- Appendix J. Noise and Vibration Impact Assessment
- Appendix K. Stormwater and Flooding Report
- Appendix L. Heritage Impact Statement
- Appendix M. Wind Impact Report
- Appendix N. Ecological Constraints Statement
- Appendix O. Bushfire Risk Assessment
- Appendix P. Environmental Site Assessment - Contamination
- Appendix P. Environmental Site Assessment - Geotechnical Re
- Appendix Q. Services Infrastructure Assessment
- Appendix R. Ecologically Sustainable Development Report
- Disclaimer
- Environmental Impact Statement_SSD 8784
- Survey - DGL - B03846-G-B03846-1 issued 04092017
- Survey - DGL - B03846-G-B03846-2 issued 04092017
Response to Submissions10
- Appendix A. Urban Design Report
- Appendix B. Urban Design Drawing Set
- Appendix C. Economic Response Letter
- Appendix D. Traffic and Transport Memorandum
- Appendix E. Noise and Vibration Assessment
- Appendix F. Design Excellence Strategy
- Appendix G. Ecologically Sustainable Development
- Department's Request for RTS - Schedule 1
- Department's Request for Response to Submissions
- Response to Submissions Report - SSD 8784
Agency Advice9
- DOC19 660138-1 Metro SI - OUT DPE - No Interest letter -
- FINAL NCA 6 2017 EIS Comments Sent to Department
- Parramatta Council - RTS sub
- Public RTS Submission 1_Redacted
- Public RTS Submission 2_Redacted
- Public Submission 3_Redacted
- RMS response at RTS stage
- RMS_ResponseLetter
- Sydney Metro comments at RTS stage
Additional Information10
- Attachment A - Response to DPIE
- Attachment B - Design Report
- Attachment B - Drawing Set
- Attachment C - Indicative Photomontage
- Attachment D - Response to Transport for NSW
- Attachment E - Response to Parramatta Council
- Attachment F - Hill PDA Letter
- Attachment G - Design Excellence Strategy
- RFI Request for Additional Information_20122019_105224
- Request For Information Response Letter
Determination6
What's near it
Where it is
- Suburb
- Epping
- Council area
- Parramatta
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.