Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its SSD-91297457 Issued SEARs on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 70 MW data centre at 23-25 Waterloo Road, Macquarie Park

The proponent proposes to build and operate a data centre at 23-25 Waterloo Road, Macquarie Park, in the City of Ryde. It would have a total power consumption of 70 MW and a building height of 64 m. It would also include office space, diesel storage, back-up generators, basement car parking, landscaping and a new road. No capital investment or job numbers are stated.

The case is at the stage where the proponent prepares its environmental impact statement (EIS). The Planning Secretary issued the environmental assessment requirements (SEARs) on 16 Sep 2025. They list the issues the EIS must address, including noise, air quality, traffic, flooding and visual impact. No submissions have been made. Next, the proponent lodges the EIS, which is exhibited so the public can make submissions. The department then assesses the project.

Total power consumption
70 MWSSD-91297457 Issued SEARs
Building height
64 mSSD-91297457 Issued SEARs

The department's description

Construction and operation of a data centre with total power consumption of 70 megawatts at 23-25 Waterloo Road, Macquarie Park

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.