On the map
State significant development

NEXTDC S5 Data Centre and Innovation Hub

90 MW data centre and innovation hub at Lane Cove Road, Macquarie Park

Under way: at assessmentData centresDistrict scale

Where it is in the process

At assessment

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (current stage)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its EIS - NEXTDC S5 Data Centre and Innovation Hub on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

90 MW data centre and innovation hub at Lane Cove Road, Macquarie Park

The proponent proposes a data centre and innovation hub at 269 Lane Cove Road, Macquarie Park, in the City of Ryde. It would be built in two stages, with a total power consumption of 90 megawatts. The data centre would have ancillary office and innovation floor space, ground floor retail, an urban plaza and new roads. Existing structures would be demolished first. No capital investment, floor area or building height is stated.

The environmental impact statement (EIS) is dated 9 Jul 2024. It drew 9 submissions: 5 objecting, 1 supporting and 3 commenting. The proponent has since amended the project and responded to submissions. The case is now at the stage where the department has asked for more information. Next, the department assesses the project and then decides it.

Total power consumption
90 MWEIS - NEXTDC S5 Data Centre and Innovation Hub
Public submissions
9 submissionsPortal page
Submissions objecting
5 submissionsPortal page

The department's description

Demolition of existing structures, site preparation works and construction and operation of a new Data Centre and Innovation Hub with urban plaza and the delivery of new roads.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

9 submissions: 6 from the public, 1 from organisations and 2 from public authorities

Object5
Support1
Comment3

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

138 documents in 9 folders, each on the NSW Planning Portal

Notice of Exhibition1
Early Consultation2
Request for SEARs2
SEARs3
EIS38
Response to Submissions3
Agency Advice29
Amendments45
Additional Information15

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.