192 Narellan Road Data Centre, Campbelltown

A 100 MW data centre at 192 Narellan Road, Campbelltown

Under way: at searsData centresRegional scale

Where it is in the process

At sears

  1. SEARs (current stage)
  2. Prepare EIS (to come)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its SEARs Scoping Report - 192 Narellan Road - v3 on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 100 MW data centre at 192 Narellan Road, Campbelltown

The proponent proposes a data centre at 192 Narellan Road, Campbelltown, in the Campbelltown council area, operating 24 hours a day. It would have a total capacity of 100 MW. It would be built in two stages: a two-storey building up to 26 m high, then a three-storey building up to 30 m high. The scoping report says the capital investment would exceed $1 billion. The buildings would sit on the 5.9 ha northern part of a 12.71 ha site.

The case is at the stage of preparing the Secretary's environmental assessment requirements (SEARs). The proponent's scoping report, dated October 2026, asks the department to set what the environmental impact statement (EIS) must cover. Next, the SEARs are issued and the proponent prepares the EIS, which is then exhibited for public submissions. No submissions have been made yet. A separate planning proposal with the council seeks to lift the site's height limit from 15 m to 30 m.

Capital investment (more than)
$1bnSEARs Scoping Report - 192 Narellan Road - v3
Power capacity
100 MWSEARs Scoping Report - 192 Narellan Road - v3
Stage 1 building height
26 mSEARs Scoping Report - 192 Narellan Road - v3
Maximum building height
30 mPortal page
Site area
12.71 haSEARs Scoping Report - 192 Narellan Road - v3
Developable northern precinct
5.9 haSEARs Scoping Report - 192 Narellan Road - v3

The department's description

Construction and 24/7 operation of a 100 megawatt data centre with a maximum building height of 30m

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.