On the map
Part 4 development

1 Foundation Place Prospect

Decided: approvedMixed use

Where it is in the process

Approved

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination (done)
  10. Approved

What it proposes

The portal gives no description.

Modifications

8 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 8 - Addition of tenancy sign to building 5DA71-2-2003-Mod-8

Decided: approved by the Minister

Its 1 documents

1 document in 1 folder, each on the NSW Planning Portal

Determination1

See the document on the Planning Portal

Its page on the Planning Portal

Mod 7 - Building 4 signage & additional windowsDA71-2-2003-Mod-7

Decided: approved by the Minister

Its page on the Planning Portal

Mod 6 - Building 3 including a roller shutterDA71-2-2003-Mod-6

Decided: approved by the department (director)

Its page on the Planning Portal

Mod 4 - Building 4 Mezzanine floorDA71-2-2003-Mod-4

Decided: approved by the department (director)

Its page on the Planning Portal

Mod 3 - Signage to the perimeter & Building 2DA71-2-2003-Mod-3

Decided: approved by the department (director)

Its page on the Planning Portal

Mod 2 - Minor external changes to buildings 1 & 5DA71-2-2003-Mod-2

Decided: approved by the department (director)

Its page on the Planning Portal

Mod 1 - Erection of two temporary signageDA71-2-2003-Mod-1

Decided: approved by the Minister

Its page on the Planning Portal

Mod 5 - Minor change to Approval PlansDA71-2-2003-Mod-5

Decided: approved on 31 Jan 2005 by the Minister

Its 8 documents

8 documents in 1 folder, each on the NSW Planning Portal

Determination8

See the 8 documents on the Planning Portal

Its page on the Planning Portal

What's near it

Its point is approximate (the register's own, to about a kilometre), and so are these.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.