Approved

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination (done)
  10. Approved

What it proposes

The portal gives no description.

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

Mod 1 - Increase of warehouse floor areaDA200-08-2004-Mod-1

Decided: approved on 19 Sep 2005 by the Minister

Its 1 documents

1 document in 1 folder, each on the NSW Planning Portal

Determination1

See the document on the Planning Portal

Its page on the Planning Portal

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.