1-5 Khartoum Road Data Centre

A 76.4 MW data centre on Khartoum Road, Macquarie Park

Decided: approved on 11 Mar 2026Data centresDistrict scale

Where it is in the process

Approved on 11 Mar 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination11 Mar 2026 (done)
  9. Approved11 Mar 2026

What it proposes

AI summary. Written from this project's page and its SSD Assessment Report and Signed - SSD Determination Instrument on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 76.4 MW data centre on Khartoum Road, Macquarie Park

The project is a data centre at 1-5 Khartoum Road, Macquarie Park, in the City of Ryde. The assessment report describes a 76.4 MW facility with a gross floor area of 19,434 m², up to 45 m high, with backup generators, cooling plant and diesel and battery storage. It would replace an existing car park, removing 64 trees. The estimated cost of development is $718,259,656. Construction would take 33 months.

The environmental impact statement was exhibited from 6 Mar 2025 to 2 Apr 2025 and drew 4 submissions: 3 objecting and 1 commenting. The department's assessment focused on noise, air quality and design, and found the project approvable with conditions. A director of the department, acting as the Minister's delegate, approved it on 11 Mar 2026. Next, the applicant must meet the conditions, including noise and air quality management plans, before and during construction.

Estimated development cost
$718.3MSSD Assessment Report
Power capacity
76.4 MWSSD Assessment Report
Gross floor area
19,434 m²SSD Assessment Report
Maximum building height
45 mPortal page
Trees to be removed
64 treesSSD Assessment Report
Construction period
33 monthsSSD Assessment Report
Public submissions
4 submissionsPortal page

The department's description

Construction and operation of a 5 storey data centre with a building height of 45 m and a capacity of 35 MW, diesel storage, part road construction, landscaping, carparking and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

4 submissions: 2 from the public, 1 from organisations and 1 from public authorities

Object3
Support0
Comment1

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

98 documents in 8 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs2
SEARs2
EIS34
Response to Submissions14
Agency Advice23
Additional Information19
Determination3

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.