On the map
State significant development

Wollar Solar Farm

Decided: approved on 24 Feb 2020Energy: solarDistrict scale

Where it is in the process

Approved on 24 Feb 2020

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination24 Feb 2020 (done)
  9. Approved24 Feb 2020

What it proposes

The department's description

Development of a 290 MW solar farm with energy storage and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

32 submissions: 16 from the public, 8 from organisations and 8 from public authorities

Object0
Support23
Comment9

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

5 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 1 - Realignment of site access and subdivision for the substationSSD-9254-Mod-1

Withdrawn: withdrawn

Relocation of the section of the main site access route which traverses the TransGrid substation lot and for subdivision of land within the solar farm to create a separate parcel for electrical assets

Its page on the Planning Portal

Wollar Solar Mod 5 - BESS CapacitySSD-9254-Mod-5

Decided: approved on 16 Oct 2026 by the department (director)

Increase in BESS storage capacity

Its 4 documents

4 documents in 3 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Wollar Solar Mod 4 - BESS CapacitySSD-9254-Mod-4

Decided: approved on 2 Apr 2026 by the department (deputy secretary) · 70 submissions

Increase in BESS capacity from the approved 30MW / 30MWh to approximately 280MW / 560MWh, as well as revised infrastructure layout

Its 25 documents

25 documents in 6 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application9

See the 9 documents on the Planning Portal

Response to Submissions5

See the 5 documents on the Planning Portal

Agency Advice6

See the 6 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 3 – changes to vehicle movements and increase in panel heightSSD-9254-Mod-3

Decided: approved on 23 Aug 2022 by the department (director) · 5 submissions

Changes to vehicle movements and increase in panel height

Its 19 documents

19 documents in 6 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application11

See the 11 documents on the Planning Portal

Response to Submissions1

See the document on the Planning Portal

Agency Advice2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Mod 2 - Site Access and SubdivisionSSD-9254-Mod-2

Decided: approved on 12 Nov 2020 by the department (director)

Realignment of site access and subdivision, biodiversity offset credits recalculation, increase in over dimensional vehicles and administrative update to schedule of land

Its 5 documents

5 documents in 3 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.