Wollar Solar Farm
Where it is in the process
Approved on 24 Feb 2020
What it proposes
The department's description
Development of a 290 MW solar farm with energy storage and associated infrastructure.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
32 submissions: 16 from the public, 8 from organisations and 8 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Modifications
5 changes to the project after its decision, each assessed as a case of its own, newest first.
Mod 1 - Realignment of site access and subdivision for the substationSSD-9254-Mod-1
Relocation of the section of the main site access route which traverses the TransGrid substation lot and for subdivision of land within the solar farm to create a separate parcel for electrical assets
Wollar Solar Mod 5 - BESS CapacitySSD-9254-Mod-5
Increase in BESS storage capacity
Its 4 documents
4 documents in 3 folders, each on the NSW Planning Portal
Modification Application1
Determination2
Consolidated Consent1
Wollar Solar Mod 4 - BESS CapacitySSD-9254-Mod-4
Increase in BESS capacity from the approved 30MW / 30MWh to approximately 280MW / 560MWh, as well as revised infrastructure layout
Its 25 documents
25 documents in 6 folders, each on the NSW Planning Portal
Notice of Exhibition1
Modification Application9
Response to Submissions5
Agency Advice6
Determination3
Consolidated Consent1
MOD 3 – changes to vehicle movements and increase in panel heightSSD-9254-Mod-3
Changes to vehicle movements and increase in panel height
Its 19 documents
19 documents in 6 folders, each on the NSW Planning Portal
Notice of Exhibition1
Modification Application11
Response to Submissions1
Agency Advice2
Determination3
Consolidated Consent1
Mod 2 - Site Access and SubdivisionSSD-9254-Mod-2
Realignment of site access and subdivision, biodiversity offset credits recalculation, increase in over dimensional vehicles and administrative update to schedule of land
Its 5 documents
5 documents in 3 folders, each on the NSW Planning Portal
Modification Application2
Determination2
Consolidated Consent1
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
60 documents in 12 folders, each on the NSW Planning Portal
Request for SEARs1
Response to Submissions2
Amendments2
Additional Information1
Determination3
Management Plans and Strategies24
Independent Reviews and Audits2
Notifications1
Other Documents9
What's near it
Where it is
- Suburb
- Tichular
- Council area
- Mid-Western Regional
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.