On the map
State significant development

Wetherill Park Data Centre

A 238 MW data centre at 2 Davis Road, Wetherill Park

Under way: at searsData centresDistrict scale

Where it is in the process

At sears

  1. SEARs (current stage)
  2. Prepare EIS (to come)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Scoping Report - Wetherill Park Data Centre on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 238 MW data centre at 2 Davis Road, Wetherill Park

The proponent proposes a 24/7 data centre at 2 Davis Road, Wetherill Park, in the Fairfield City Council area. It would be one four-storey building with a total capacity of about 238 MW and an IT load of 170 MW. The works include demolishing existing structures, an on-site substation and a transmission line. The site is about 43,285 m² and now holds a warehouse and distribution facility. No capital investment or job numbers are stated.

The case is at the stage of preparing the Secretary's environmental assessment requirements (SEARs). The proponent's scoping report requests them. Next, the department issues the SEARs and the proponent prepares an environmental impact statement (EIS). The EIS would then be exhibited, when the public can make submissions. No submissions have been made yet and no decision date is given.

Total capacity
238 MWPortal page
IT load
170 MWPortal page
Building height
4 storeysPortal page
Site area
43,285 m²Scoping Report - Wetherill Park Data Centre

The department's description

Construction and operation of a 24/7 data centre comprising one four-storey building with a total capacity of approx 238 MW, an IT Load of 170 MW including demolition and site establishment works, on-site substation and transmission line.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.