On the map
State significant development

Western Sydney University Bankstown City Campus

Decided: approved on 18 Feb 2021Education

Where it is in the process

Approved on 18 Feb 2021

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination18 Feb 2021 (done)
  9. Approved18 Feb 2021

What it proposes

The department's description

Construction of a 21-storey building (including two basement levels) for Western Sydney University education use and associated research space, conference facilities and retail uses. The proposal includes public domain works, landscaping and signage.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

14 submissions: 9 from the public and 5 from public authorities

Object3
Support1
Comment10

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

4 changes to the project after its decision, each assessed as a case of its own, newest first.

WSU Bankstown City Campus MOD 4 - TAFE useSSD-9831-Mod-4

Decided: approved on 24 Dec 2025 by the department (team leader)

Clarify the use of the higher education facility from “university” to “tertiary institution" to allow for TAFE to occupy the facility.

Its 7 documents

7 documents in 3 folders, each on the NSW Planning Portal

Modification Application4

See the 4 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

WSU Bankstown City Campus MOD 3 - Construction hrsSSD-9831-Mod-3

Decided: approved on 1 Aug 2022 by the department (team leader)

Amend construction hours to allow for internal fitout works to be undertaken outside of standard construction hours.

Its 7 documents

7 documents in 3 folders, each on the NSW Planning Portal

Modification Application4

See the 4 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

WSU Bankstown City Campus MOD 2 - SignageSSD-9831-Mod-2

Decided: approved on 19 May 2022 by the department (team leader)

Modification to increase the width of the approved signage zone on the southern building facade from 20.7m to 26.5m.

Its 11 documents

11 documents in 4 folders, each on the NSW Planning Portal

Modification Application4

See the 4 documents on the Planning Portal

Additional Information3

See the 3 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

WSU Bankstown City Campus MOD 1 - Site descriptionSSD-9831-Mod-1

Decided: approved on 8 Apr 2021 by the department (director)

Correction to site description.

Its 5 documents

5 documents in 3 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.