On the map
State significant development

Wenona School - Education Building

Decided: approved on 18 Dec 2015Education

Where it is in the process

Approved on 18 Dec 2015

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination18 Dec 2015 (done)
  9. Approved18 Dec 2015

What it proposes

The portal gives no description.

Submissions

What the public, organisations and public authorities said, counted by where they stood.

10 submissions: 2 from the public and 8 from organisations

Object3
Support1
Comment6

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

4 changes to the project after its decision, each assessed as a case of its own, newest first.

Wenona School MOD 4 - Relocation of substationWenona School MOD 4 - Relocation of substationSSD-6952-Mod-4

Decided: approved on 17 Jun 2019 by the department (director)

Relocation of approved electrical substation

Its 2 documents

2 documents in 2 folders, each on the NSW Planning Portal

Early Consultation1

See the document on the Planning Portal

Modification Application1

See the document on the Planning Portal

Its page on the Planning Portal

Wenona School MOD 2 - Substation and treesSSD-6952-MOD-2

Decided: approved on 21 Nov 2018 by the department (executive director)

.

Its 19 documents

19 documents in 3 folders, each on the NSW Planning Portal

Application9

See the 9 documents on the Planning Portal

Additional Information7

See the 7 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Wenona School MOD 3 - Frontage, Works, DesignSSD-6952-MOD-3

Decided: approved on 21 Sep 2018 by the department (director)

.

Its 7 documents

7 documents in 2 folders, each on the NSW Planning Portal

Application4

See the 4 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Mod 1SSD-6952-MOD-1

Decided: approved on 23 Feb 2017 by the department (director)

Its 14 documents

14 documents in 3 folders, each on the NSW Planning Portal

Application11

See the 11 documents on the Planning Portal

Submissions1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.