State significant development

Waste Management Facility, Botany

A 300,000 tonne a year waste facility at Hale Street, Botany

Decided: approved on 29 May 2026WasteLocal scale

Where it is in the process

Approved on 29 May 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination29 May 2026 (done)
  9. Approved29 May 2026

What it proposes

AI summary. Written from this project's page and its SSD Instrument of Consent - 29 May 2026 and SSD-SSI Assessment Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 300,000 tonne a year waste facility at Hale Street, Botany

The project is a waste transfer station at 2-4 Hale Street, Botany, in the Bayside area, on an industrial site of 7,439.3 m² next to Sydney Airport. It would accept up to 300,000 tonnes a year of non-putrescible construction and demolition waste, which is sorted and stored briefly in a warehouse before going to recycling facilities. The warehouse is up to 17 m high. The estimated cost is $15,575,000, with 12 construction jobs and 11 operational jobs. It would operate 24 hours a day, 7 days a week.

The environmental impact statement (EIS) was exhibited from 7 Aug 2024 to 3 Sep 2024 and drew 29 submissions: 28 objecting and 1 commenting. The proponent responded and gave more information several times. The department recommended approval, and its Executive Director, as the Minister's delegate, approved the project with conditions on 29 May 2026. Next, the proponent must meet those conditions before construction and operation.

Capital investment
$15.6MSSD-SSI Assessment Report
Waste capacity
300,000 tonnes a yearSSD-SSI Assessment Report
Construction jobs
12 jobsSSD-SSI Assessment Report
Operational jobs
11 jobsSSD-SSI Assessment Report
Site area
7,439.3 m²SSD-SSI Assessment Report
Maximum building height
17 mSSD-SSI Assessment Report
Heavy vehicles a day
175 vehiclesSSD-SSI Assessment Report
Public submissions
29 submissionsSSD-SSI Assessment Report

The department's description

Construction and operation of a waste management facility with a capacity to process up to 300,000 tpa of construction & demolition waste, including new hardstand, purpose built warehouse, office and amenities, and two new crossovers.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

29 submissions: 26 from the public and 3 from organisations

Object28
Support0
Comment1

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

113 documents in 8 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs2
SEARs3
EIS27
Response to Submissions19
Agency Advice26
Additional Information31
Determination4

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.