On the map
State significant development

Vickery Mine Extension

Decided: approved on 12 Aug 2020Mining

Where it is in the process

Approved on 12 Aug 2020

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination12 Aug 2020 (done)
  9. Approved12 Aug 2020

What it proposes

The department's description

Extension of the approved Vickery Coal Mine, including a coal handling and preparation plant (CHPP), train load-out facility and rail spur line (see attached Environmental Impact Statement).

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

575 submissions: 479 from the public and 96 from organisations

Object202
Support345
Comment28

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

3 changes to the project after its decision, each assessed as a case of its own, newest first.

MOD 3 - Coal HaulageSSD-7480-Mod-3

Decided: approved on 5 Aug 2026 by the department (director) · 9 submissions

Increase to ROM coal haulage limits

Its 18 documents

Its page on the Planning Portal

MOD 2 - Increase to 2025 Coal Haulage LimitSSD-7480-Mod-2

Decided: approved on 8 Oct 2025 by the department (director)

Increase of an additional 0.3 Mtpa of ROM coal along the southern section of the approved ROM coal haulage route (to a combined total of 3.8 Mtpa ROM coal) to the Whitehaven CHPP for calendar year 2025

Its 15 documents

15 documents in 6 folders, each on the NSW Planning Portal

Early Consultation1

See the document on the Planning Portal

Modification Application4

See the 4 documents on the Planning Portal

Agency Advice4

See the 4 documents on the Planning Portal

Additional Information3

See the 3 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 1 - Waste Tyres, Road Haulage and Concrete Batch PlantSSD-7480-Mod-1

Decided: approved on 7 Aug 2025 by the department (director) · 14 submissions

Modification to allow for the disposal of heavy vehicle waste tyres in the waste rock emplacement areas, extended run-of-mine (ROM) coal road haulage hours and the establishment and use of a concrete batching plant

Its 41 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.