Thrumster Wastewater Scheme
A wastewater treatment plant and pipelines at Fernbank Creek
Where it is in the process
Approved on 4 Jun 2026
What it proposes
AI summary. Written from this project's page and its Instrument of approval and SSI Assessment Report on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A wastewater treatment plant and pipelines at Fernbank Creek
Port Macquarie-Hastings Council proposed a wastewater treatment plant and a recycled water treatment plant at 433 Fernbank Creek Road, Fernbank Creek, with about 33 kilometres of collection, distribution and discharge pipelines. The plant would have an initial design capacity for 40,000 equivalent population. The department gives a capital investment of $134 million, 120 construction jobs and four operational jobs. It would service over 7,000 additional homes.
The environmental impact statement (EIS) was exhibited from 6 Aug 2024. The proponent then amended the project, and the amended application was re-exhibited from 8 May 2025 to 21 May 2025. The portal records 117 submissions: 103 objecting, 11 supporting and 3 commenting. The department recommended approval and the Minister approved the project on 4 Jun 2026, with conditions. Next, the proponent must meet those conditions before and during construction.
- Capital investment
- $134MSSI Assessment Report
- Pipelines length
- 33 kilometresSSI Assessment Report
- Plant design capacity
- 40,000 equivalent populationSSI Assessment Report
- Additional homes serviced
- 7,000 homesSSI Assessment Report
- Construction jobs
- 120 jobsSSI Assessment Report
- Operational jobs
- 4 jobsSSI Assessment Report
- Submissions
- 117 submissionsPortal page
The department's description
Construction of a wastewater treatment plant and associated sewage and reuse mains'.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
117 submissions: 103 from the public and 14 from organisations
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
82 documents in 13 folders, each on the NSW Planning Portal
Early Consultation3
Notice of Exhibition2
EIS22
- Environmental Impact Statement_Thrumster WWS
- TR 1A - Water Res and Flooding Assessment _ Thrumster WWS
- TR1 B-Operational Water Quality Imp Assess -Thrumster WWS
- TR10 - Waste and Chemicals Assessment - Thrumster WWS
- TR11 - Noise and Vibration Assessment - Thrumster WWS
- TR12 - Health Impact Assessment - Thrumster WWS
- TR13 - Landscape Char and Visual Assess - Thrumster WWS
- TR14 - Bushfire Risk Assessment - Thrumster WWS
- TR15 - Preliminary Hazard Analysis - Thrumster WWS
- TR16 - ESD - Thrumster WWS
- TR17 - Climate Risk Assessment - Thrumster WWS
- TR18 - Greenhouse Gas Assessment - Thrumster WWS
- TR19 - Aviation Impact Assessment - Thrumster WWS
- TR2-ACHA_PUBLIC EXHIBITION - Thrumster WWS
- TR3 - Historical Heritage Assessment - Thrumster WWS
- TR4 - Social Impact Assessment - Thrumster WWS
- TR5- BDAR - Thrumster WWS
- TR6 - Aquatic Ecology Assessment - Thrumster WWS
- TR7 - Traffic and Transport Assessment - Thrumster WWS
- TR8 - Air Quality Assessment - Thrumster WWS
- TR9 - Soils and Contam - Thrumster WWS
- Thrumster WWS - Concept Design Report WWTP
Response to Submissions7
Agency Advice34
- 2023-04-06 DPI Ag EARS SSI-56980459
- 20240808_DPIresp_Thrumster Wastewater Scheme (SSI-56980459)
- BCD Resp -Thrumster Wastewtr Sch SSI 56980459
- BCS Response Thrumster Wastewater Sch SSI56980459
- C23-190 SEARs SSI-56980459 DPI Fisheries advice
- C24-717 EIS comments SSI-56980459
- DCCEEW BCS and NPWS Response - Thrumster Wastewater Scheme
- DCCEEW CPHR Rsp Thrumst WWS RTS Sgn GP 14-05-2025
- DCCEEW Response - Thrumster WWS - RTS - SSI-56980459
- DPE Water - Thrumster Wastewater - SEARS(2)
- EPA - 27.05.25
- EPA SEARs
- HMS 6888
- HNSW - ACH - Advice on SEARs - SSI-56980459
- HNSW ACH - EIS - Thrumster Wastewater Scheme - SSI-56980459
- HNSW ACH - RTS Amendment - Thrumster - SSI-56980459
- Letter Out - Thrumster Wastewater Scheme - EIS
- NSW DCCEEW Water Group response
- NSW DCCEEW Water Group response
- NSW Resources Response - Thrumster Wastewater Scheme -EIS
- NSW SES Response Advice on EIS Thrumster Wastewater Scheme
- NTH24_00279_004 - 20240820 - TfNSW Response - SSI-56980459
- OUT25-5912 SSI-56980459 DPIRD Fisheries comments
- SSI Comment letter - SEARs AppId2631PAE-56986239
- TfNSW Response
- Thrumster WWS_RTS_DPIRD Ag and Bio Advice
- Thrumster WWTP SSI 56980459 CASA comments
- Thrumster Wastewater & Recycled Water project
- Thrumster Wastewater Scheme
- Thrumster Wastewater Scheme (SSI-56980459) Response Letter
- Thrumster Wastewater Scheme - Response letter
- Thrumster Wastewater Scheme - SSI 56980459 TfNSW Response
- Thrumster Wastewater Scheme SSI-56980459
- Thrumster_RFS_18.4.23
Additional Information2
Post-determination Notices2
Management Plans and Strategies2
Notifications1
Other Documents1
What's near it
Where it is
- Suburb
- Fernbank Creek
- Council area
- Port Macquarie-Hastings
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.