On the map
State significant development

Texas Solar Farm

A 400 MW solar farm and battery on Bruxner Way, Texas

Under way: at prepare eisEnergy: solarDistrict scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Texas Solar Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 400 MW solar farm and battery on Bruxner Way, Texas

The proponent proposes a solar farm of up to 400 MW and a battery energy storage system of up to 200 MW / 800 MWh, on rural land at 13738 Bruxner Way, Texas, in the Inverell Shire Council area, near the Queensland border. The site is about 1,600 ha. The solar farm may take about 950 ha, the battery 8 ha and the switching station and substation 3 ha. It would connect to the existing 330 kV transmission line that crosses the site. No capital investment figure is stated beyond "more than $30 million".

The case is at the stage where the proponent prepares its environmental impact statement (EIS). A scoping report dated 22 Mar 2024 was lodged, and the Secretary's environmental assessment requirements (SEARs) have been issued, with a supplementary set. No submissions have been made. Next, the EIS is to be exhibited for public submissions, then the department assesses it.

Solar farm capacity
400 MWTexas Solar Scoping Report
Battery power capacity
200 MWPortal page
Battery storage capacity
800 MWhPortal page
Site area
1,600 haTexas Solar Scoping Report
Possible solar farm area
950 haTexas Solar Scoping Report
Possible battery area
8 haTexas Solar Scoping Report
Grid connection voltage
330 kVTexas Solar Scoping Report

The department's description

Construction, operation, and decommissioning of a 400MW solar farm and Battery Energy Storage System with a capacity of 200MW/800MWh. The development will also include associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Where it is

Suburb
Texas
Council area
Inverell

Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.