Temora Battery Energy Storage System
An 80 MW battery at 108 Miners Street, Temora
Where it is in the process
At collate submissions
What it proposes
AI summary. Written from this project's page and its Temora BESS EIS on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
An 80 MW battery at 108 Miners Street, Temora
The proponent proposes a battery energy storage system with about 80 MW of power and 364 MWh of storage at 108 Miners Street, Temora, in Temora Shire, about 1 km south-east of the town. It would include an on-site substation, an overhead connection to the adjoining Essential Energy Temora Zone Substation, and upgrades to Miners Street. Construction would employ an average of 40 to 60 workers and the operation 2-3 full-time equivalent staff. No capital investment is stated.
The environmental impact statement (EIS), dated 24 September 2026, has been exhibited. The portal lists the case at the stage of collating submissions, with 40 received: 38 objecting, 1 supporting and 1 commenting. Next, the proponent responds to the submissions and may amend the project. The department then assesses it and the decision follows. No decision date is given.
- Battery power capacity
- 80 MWTemora BESS EIS
- Battery storage capacity
- 364 MWhTemora BESS EIS
- Peak construction workforce
- 80 workersTemora BESS EIS
- Development footprint
- 4.6 haTemora BESS EIS
- Native vegetation to be cleared
- 4.09 haTemora BESS EIS
- Public submissions
- 40 submissionsPortal page
The department's description
Construction, operation, and decommissioning of a battery energy storage system (BESS) with a capacity of 80MW/364MWh and ancillary infrastructure.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
40 submissions: 32 from the public and 8 from organisations
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
35 documents in 5 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs1
SEARs1
EIS18
- Appendix E - SLAIA Rpt
- Appendix F - FIRA Rpt
- Appendix G - BHA Rpt
- Appendix H - Engagement Rpt
- Appendix I - SEIA Rpt
- Appendix J - BDAR Rpt
- Appendix K - ACHAR Rpt
- Appendix L - SOHI Rpt
- Appendix M - TIA Rpt
- Appendix N - NVA Rpt
- Appendix O - LCVIA Rpt
- Appendix P - PHA Rpt
- Appendix Q - Air quality Rpt
- Appendix R - Risk assessment Rpt
- Appendix S - PWMP
- EDC - Temora BESS
- Temora BESS EIS
- Temora BESS EIS Summary Rpt
Agency Advice14
- Advice SEARS - Temora Council
- Advice SEARs - BCS
- Advice SEARs - Crown Lands
- Advice SEARs - DPI Agriculture
- Advice SEARs - DPIRD NSW Resources (MEG)
- Advice SEARs - Fire + Rescue NSW
- Advice SEARs - Heritage NSW (ACH)
- Advice SEARs - NSW DCCEEW Water
- Advice SEARs - Transport for NSW
- Advice on EIS - Crown Lands
- Advice on EIS - DPIRD Agriculture
- Advice on EIS - DPIRD NSW Resources
- Advice on EIS - FRNSW
- Advice on EIS - NSW DCCEEW MCEF
What's near it
Where it is
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.