Telopea Concept Plan and Stage 1A
423 homes in five apartment buildings at Telopea Stage 1A
Where it is in the process
Approved on 28 May 2026
What it proposes
AI summary. Written from this project's page and its Assessment Report and Instrument on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
423 homes in five apartment buildings at Telopea Stage 1A
The project is Stage 1A of the Telopea redevelopment, at Sturt Street and Polding Place, Telopea, in the City of Parramatta. It has five apartment buildings of 6 to 15 storeys with 423 apartments: 146 social, 99 affordable and 178 market homes. It has a total gross floor area of 32,911 m² on a site of about 20,594 m². A new plaza and park of 5,952 m² and road upgrades are included. No capital investment is stated.
The application first included a concept plan for the wider precinct. It was exhibited from 13 Oct 2021 to 9 Nov 2021, and again from 4 Dec 2025 to 17 Dec 2025 after the concept plan was removed. The portal records 40 submissions: 28 objecting, 3 supporting and 9 commenting. The department recommended approval, and the Minister approved it on 28 May 2026, with conditions. Next, the proponent must meet the conditions, including a planning agreement with the council, before building.
- New apartments
- 423 dwellingsAssessment Report
- Social housing dwellings
- 146 dwellingsAssessment Report
- Affordable housing dwellings
- 99 dwellingsAssessment Report
- Market housing dwellings
- 178 dwellingsAssessment Report
- Maximum building height
- 15 storeysAssessment Report
- Gross floor area
- 32,911 m²Assessment Report
- Public plaza and park
- 5,952 m²Assessment Report
- Site area
- 20,594 m²Assessment Report
The department's description
Concept proposal for the redevelopment of the site as a mixed-use development, including 4,700 dwellings, retail and commercial uses, community facilities, public open space and new roads. Stage 1A proposal for first stage of development.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
40 submissions: 35 from the public, 4 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Modifications
1 change to the project after its decision, each assessed as a case of its own, newest first.
Modification 1 Telopea Concept Plan and Stage 1ASSD-14378717-Mod-1
Deletion of Condition C29 (Security Deposit) and Condition E12 (Maintenance Bond) and amendment to Condition E6
Its 9 documents
9 documents in 3 folders, each on the NSW Planning Portal
Modification Application6
Determination2
Consolidated Consent1
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
384 documents in 11 folders, each on the NSW Planning Portal
Notice of Exhibition2
Development Application3
EIS69
- Appendix AA_Utilities Report
- Appendix A_SEARs Response
- Appendix BB_Concept Engineering Drawings
- Appendix B_QS Cost Assessment
- Appendix CC - Stage 1A civil drawings
- Appendix C_Survey Plan
- Appendix DD_Flooding Assessment
- Appendix D_Draft Plan of Subdivision
- Appendix EE_Integrated Water Management
- Appendix E_Staging plan
- Appendix FF1_Sustainability Report
- Appendix FF2_BASIX Certificate 1
- Appendix FF3_BASIX Certificate 2
- Appendix F_Concept Masterplan Drawings
- Appendix G1_Concept Design Report
- Appendix G2_Concept Design Report
- Appendix GG1 BCA Assessment
- Appendix GG2_Access Report
- Appendix GG3_Fire safety
- Appendix HH_Acoustic Assessment
- Appendix H_Design Guidelines
- Appendix I1_Preliminaries
- Appendix I2_General Arrangements
- Appendix I3_Elevations
- Appendix I4_Solar Cross Vent
- Appendix I5_DDA Plans
- Appendix I6_External Finishes
- Appendix I7_Perspectives
- Appendix I8_Development Schedules
- Appendix II_Waste Management
- Appendix JJ1_Wind Masterplan
- Appendix JJ2_Wind Stage 1A
- Appendix J_Stage 1A Design Report
- Appendix KK_Construction Management Plan
- Appendix K_Stage 1A Landscape Plans
- Appendix L1_Stage 1A Landscape Report
- Appendix L2_Stage 1A Public Domain
- Appendix LL_Connecting with Country
- Appendix MM_SDRP Responses
- Appendix M_Consultation Report
- Appendix NN_Mitigation Measures & Risk Assessment
- Appendix N_Clause 4.6 Variation Concept Plan
- Appendix OO_Electrolysis Report
- Appendix O_Clause 4.6 Variation Stage 1A
- Appendix P1_Visual Impact
- Appendix P2_Photomontage Masterplan
- Appendix P3_Photomontage Stage 1A
- Appendix PP_Design Excellence Strategy
- Appendix Q_Social Needs Assessment
- Appendix RR_Isolated Lot Study
- Appendix R_Social Impact Assessment
- Appendix S_CPTED
- Appendix T_Traffic
- Appendix U_Biodiversity Report
- Appendix V1_Arborist
- Appendix V2_Arborist
- Appendix W_Aboriginal Cultural Heritage
- Appendix X_Heritage Impact
- Appendix Y1_Geotechnical Masterplan
- Appendix Y2_Geotechnical Stage 1A
- Appendix Y3_Rail Corridor
- Appendix Z1_Preliminary Site Investigation
- Appendix Z2_Detailed Site Investigation
- Appendix Z3_Stage 1A DSI Letter
- Application_20210730082516
- Council VPA letter of offer October 2021
- Environmental Impact Statement_Telopea_2021
- State VPA letter of offer October 2021
- Telopea_Site Detail
Response to Submissions58
- Amended RTS_ Basix and NatHERs
- Amended RTS_App B - Design Report
- Amended RTS_App C - Architectural Plans
- Amended RTS_App D - Design Excellence Review
- Amended RTS_App E - Building A Waste Diagram
- Amended RTS_App F - Landscape Report
- Amended RTS_App G - Landscape Plans
- Amended RTS_App H - Revised Arboricultural
- Amended RTS_App I - Transport Response
- Amended RTS_App J - Flood Impact Assessment
- Amended RTS_App K - Water Management Plan
- Amended RTS_App L - Civil Plans
- Amended RTS_App M - Subdivision
- Amended RTS_Submissions Report
- Appendix A - Submissions Register
- Appendix AA - Stage 1A Traffic and Parking Statem
- Appendix B - Updated Mitigation Measures
- Appendix BB - PDA Program
- Appendix C - List of Plans for Approval
- Appendix CC - Progress Consultation Report
- Appendix D - QS Report
- Appendix DD1 - Stage 1A Plans
- Appendix DD2 - Stage 1A floor plans
- Appendix DD3 - Stage 1A elevations
- Appendix DD4 - Stage 1A solar
- Appendix DD5 - Stage 1A cross vent
- Appendix DD6 - Stage 1A GFA calcs
- Appendix DD7 - Stage 1A DDA plans
- Appendix DD8 - Stage 1A finishes
- Appendix DD9 - Stage 1A perspectives
- Appendix E - Concept Masterplan Drawings
- Appendix F - Concept RTS Design Report
- Appendix G - Design Guidelines
- Appendix H - Design Excellence Strategy
- Appendix I - Masterplan Civil Drawings
- Appendix J - Stage 1A Design Report Pt 1
- Appendix J - Stage 1A Design Report Pt 2
- Appendix K1 - Stage 1A Landscape Concept Plan Pt 1
- Appendix K1 - Stage 1A Landscape Concept Plan Pt 2
- Appendix K2 - Stage 1A Landscape Concept Plan
- Appendix L - Stage 1A Landscape Plans
- Appendix M - Stage 1A Public Domain Plans
- Appendix N - Stage 1A Civil Drawings
- Appendix O - Height CPA Clause 4.6 Request
- Appendix P - Height Stage 1A Clause 4.6 Request
- Appendix Q - FSR CPA Clause 4.6 Request
- Appendix R - Addenda Flood Assessment
- Appendix S - Stage 1A Subdivision Plans
- Appendix T - Dedication Plan
- Appendix U - SDRP Feedback (Session 3)
- Appendix V - State VPA Letter to Formal Offer
- Appendix W - Electrolysis Report
- Appendix X - Noise Impact Assessment
- Appendix Y - BDAR Waiver
- Appendix Z - Historical Archaeology Report
- LAHC Approval - RTS
- RFI Request_submissions report
- Telopea - Submissions Report
Agency Advice43
- Amendment - CPHR
- Amendment - Council
- Amendment - TfNSW
- EIS - Council Attachment A
- EIS - Council Attachment B
- EIS - Council Cover Letter
- EIS - Council Submission
- EIS - DPIE SIA team
- EIS - EESG
- EIS - EPA
- EIS - Heritage (ACH)
- EIS - Heritage NSW
- EIS - Sydney Water
- EIS - TfNSW
- EIS - Western Sydney Local Health District
- RRTS - Council
- RRTS - Council Attachment A
- RRTS - Council Attachment B
- RRTS - EHG
- RRTS - TfNSW
- RtS - Council
- RtS - Council Attachment A
- RtS - Council Attachment B
- RtS - Endeavour Energy
- RtS - Heritage (ACH)
- RtS - Heritage NSW
- RtS - TfNSW
- RtS - TfNSW 2
- RtS - Western Sydney Local Health District
- RtS- EHG
- RtS-Sydney Water
- SEARS - EPA
- SEARS - Sydney Trains SEARs
- SEARs - Council
- SEARs - EESG
- SEARs - Heritage (ACH)
- SEARs - Heritage NSW
- SEARs - Sydney Water
- SEARs - TfNSW
- SEARs -EPA Attachment A
- Supplementary RRtS - CoP
- Supplementary RRtS - EHG
- Supplementary RRtS - TfNSW
Amendments22
- Amended Application_20251112074808
- Amendment Report
- Appendix A - Stage 1A Revised Clause 4.6 Variation Request
- Appendix B -Stage 1A Revised Design Report
- Appendix C - Architectural Plans - Combined
- Appendix C_Architectural Plans_Part1
- Appendix C_Architectural Plans_Part2
- Appendix C_Architectural Plans_Part3
- Appendix C_Architectural Plans_Part4
- Appendix C_Architectural Plans_Part5
- Appendix C_Architectural Plans_Part6
- Appendix D - ADG Schedules
- Appendix E - Development Schedules
- Appendix F - Landscape Report
- Appendix G - Landscape Plans
- Appendix H - Aboricultural Impact Report
- Appendix I -Transport Statement
- Appendix J - Civil Plans
- Appendix K - Sustainability Strategy
- Appendix L - BASIX Report and Certificates
- Appendix M - Plan of Subdivison
- Appendix N - Waste Management Plan
Additional Information171
- Appendix A - List of Plans for Approval
- Appendix A1 - Development Schedules
- Appendix A10 - Stage 1A RFI Design Report
- Appendix A2 - Preliminaries
- Appendix A3 - Floor Plans - B02 to L6
- Appendix A3 - Floor Plans - L7 to roof
- Appendix A5 - Elevations
- Appendix A6 - Sections
- Appendix A7 - Development Amenities
- Appendix A8 - DDA Typologies
- Appendix A9 - Perspectives
- Appendix AA - Arborist Report - Stage 1A Proposal
- Appendix B - ADG Schedules
- Appendix B - Compliance Diagrams
- Appendix B - DDA Typologies
- Appendix B - Development Schedules
- Appendix B - Elevations and Sections
- Appendix B - External Finishes
- Appendix B - General Arrangement Plans
- Appendix B - Stage 1A ADG Compliance Tables
- Appendix B Part 1 - Concept Proposal Drawings
- Appendix B Part 2 - Concept Proposal Drawings
- Appendix B Part 3 - Concept Proposal Drawings
- Appendix B1 - ADG Compliance Tables for Stage 1A (Bdg A)
- Appendix B2 - ADG Compliance Tables for Stage 1A (Bdg B)
- Appendix B3 - ADG Compliance Tables for Stage 1A (Bdg C)
- Appendix B4 - ADG Compliance Tables for Stage 1A (Bdg D)
- Appendix B5 - ADG Compliance Tables for Stage 1A (Bdg E)
- Appendix BB - Arborist Report - Concept Proposal
- Appendix C - Stage 1A Traffic Advice
- Appendix C1 - Concept Response to Submissions Report
- Appendix C1 -- Telopea Masterplan Drawings - Preliminaries
- Appendix C2 - Telopea Area Schedule
- Appendix C2 -- Telopea Masterplan Drawings - Core Precinct
- Appendix C3 - Solar Access and Shadow Analysis
- Appendix C3 -- Telopea Masterplan Drawings - North Precinct
- Appendix C4 - SEPP65 Compliance Analysis
- Appendix C4 -- Telopea Masterplan Drawings - South Precinct
- Appendix C5 - Isolated Lots Study
- Appendix C5 -- Telopea Masterplan Drawings - Elevations
- Appendix C6 -- Telopea GFA Schedule
- Appendix CC1 - BASIX Report
- Appendix CC2 - NatHERS Assessment
- Appendix D - Design Guidelines
- Appendix D -- ADG Summary for Concept Works
- Appendix D1 - Concept Plans Core Precinct
- Appendix D1 - Concept Plans Core Precinct
- Appendix D2 - Concept Plans North Precinct
- Appendix D3 - Concept Plans South Precinct
- Appendix D4 - Concept Plans Street Elevations
- Appendix DD - LAHC Isolated Lots Letter
- Appendix E -- Response to Council’s Attachment A and B
- Appendix E1 - Concept ADG Compliance Tables
- Appendix E1 - Design Excellence Letter
- Appendix E2 - Design Excellence Strategy
- Appendix E2 - Solar Access and Shadow Analysis
- Appendix E3 - Stage 1A Design Excellence Waiver Request
- Appendix EE - QS Advice
- Appendix F1 - Concept Proposal Landscape Drawings
- Appendix F1 - Stage 1A Landscape Plans Public Domain 1
- Appendix F1 -- Amended BDAR Report for Concept Plan
- Appendix F2 - Concept Proposal Landscape Drawings
- Appendix F2 - Stage 1A Landscape Plans Public Domain 2
- Appendix F3 - Stage 1A Landscape Plans Residential
- Appendix F4 - Concept Landscape Plans
- Appendix G - Clause 4.6 Variation to height in Stage 1A
- Appendix G - Concept Proposal Civil Drawings
- Appendix G1 -- Amended BDAR Report for Stage 1A
- Appendix G2 -- Addendum Tree Species advice
- Appendix H - Arborist Report
- Appendix H - Stage 1A Arch Plans - DDA Typologies
- Appendix H - Stage 1A Arch Plans - Development Amenties
- Appendix H - Stage 1A Arch Plans - Elevations
- Appendix H - Stage 1A Arch Plans - External Finishes
- Appendix H - Stage 1A Arch Plans - Floor Plans
- Appendix H - Stage 1A Arch Plans - Perspectives
- Appendix H - Stage 1A Architectural Plans - Preliminaries
- Appendix H - Technical Note – TfNSW Comments
- Appendix I - Local Road Network Performance
- Appendix I - Stage 1A Design Report
- Appendix I - Stage 1A Design Report Appendices
- Appendix I - Tree Impact Assessment
- Appendix J - Civil Plans - Concept Works
- Appendix J - Stage 1A Landscape Plans
- Appendix J - Telopea GFA Schedule
- Appendix K - Civil Plans - Stage 1A Works
- Appendix K - Plan of Subdivision
- Appendix K - Stage 1A Public Domain Plan
- Appendix L - Isolated Lot Letter
- Appendix L - Stage 1A Civil Drawings
- Appendix L1 -- Stage 1A Design Report
- Appendix L1 -- Stage 1A Design Report Appendices
- Appendix L2 -- Stage 1A Solar Amenity Report
- Appendix M - Stage 1A Civil Plans
- Appendix M - Stage 1A Subdivision Plans
- Appendix M1 -- Stage 1A Architectural Plans - Preliminaries
- Appendix M10 - Stage 1A Architectural Plans - GFA Plans
- Appendix M11 - Stage 1A Architectural Plans - Open Space
- Appendix M12 - Stage 1A Architectural Plans - Perspectives
- Appendix M2 -- Stage 1A Arch Plans - GA Plans B2 to L6
- Appendix M3 -- Stage 1A Arch Plans - GA Plans L7 to Roof
- Appendix M4 - Stage 1A Architectural Plans - DDA Plans
- Appendix M5 - Stage 1A Architectural Plans - Elevations
- Appendix M6 - Stage 1A Arch Plans - Overall Elevations
- Appendix M7 - Stage 1A Architectural Plans - Sections
- Appendix M8 - Stage 1A Architectural Plans - Solar Amenity
- Appendix M9 - Stage 1A Arch Plans - Cross Ventilation
- Appendix N - Clause 4.6 Variation Concept Plan Height
- Appendix N - Concept Civil Plans
- Appendix N - Stage 1A Design Access Report
- Appendix O - Clause 4.6 Variation Stage 1A Height
- Appendix O1 - Stage 1A Strata Plan of Subdivision
- Appendix O2 - Stage 1A Stratum Plan of Subdivision
- Appendix P - Clause 4.6 Variation Concept Plan FSR
- Appendix P - Stage 1A Wind Assessment
- Appendix Q - Stage 1A BCA Report
- Appendix Q1 - Addenda Visual Impact Study
- Appendix Q2 Part 1 - VIA Methodology Report
- Appendix Q2 Part 2 - VIA Methodology Report
- Appendix R - Noise Impact Assessment
- Appendix R - Stage 1A Fire Assessment
- Appendix S - Clause 4.6 Request - Height Stage 1A
- Appendix S - Traffic Modelling Report
- Appendix T - Clause 4.6 Request - Height Concept Plan
- Appendix T1 - Addendum Stage 1A Waste Management Plan
- Appendix T2 - Waste Management Letter of Endorsement
- Appendix U - Clause 4.6 Request - FSR Concept Plan
- Appendix U - Stage 1A Wind Assessment
- Appendix V - Stage 1A BCA Report
- Appendix W - Stage 1A Access Report
- Appendix W1 - Design Excellence Waiver Cover Letter
- Appendix W2 - Design Excellence Waiver Request
- Appendix W3 - CoP Stage 1A Feedback Register
- Appendix X - Stage 1A Fire Safety Report
- Appendix X - Stage 1A Landscape Plans
- Appendix Y - Concept Proposal BDAR
- Appendix Y - Stage 1A Landscape Report
- Appendix Z - Stage 1 Proposal BDAR
- Appendix Z1 - Stage 1A Public Domain Plans
- Concept SSD - ADG Compliance Summary
- Concept SSD - Civil Plans
- Concept SSD - Core and East Precinct Plans
- Concept SSD - Landscape Masterplan
- Concept SSD - North Precinct Plans
- Concept SSD - Plan of Subdivision
- Concept SSD - Sections and Elevations
- Concept SSD - South Precinct Plans
- Revised Clause 4.6 Variation Request
- Stage 1A - ADG Compliance Tables
- Stage 1A - Civil Plans
- Stage 1A - CoP RFI addendum - Bdg A
- Stage 1A - CoP RFI addendum - Bdg B
- Stage 1A - DDA Typologies
- Stage 1A - Development Schedule
- Stage 1A - Floor Plans - B2 to L6
- Stage 1A - Floor Plans - L7 to Roof
- Stage 1A - GFA Diagrams
- Stage 1A - Landscape Plans
- Stage 1A - NatHERS Assessment
- Stage 1A - Perspectives
- Stage 1A - Plan of Subdivision
- Stage 1A - Preliminaries
- Stage 1A - Sections and Elevations
- Stage 1A - Solar Diagrams
- Stage 1A BASIX_Bdgs A,B&C
- Stage 1A BASIX_Bdgs D&E
- Telopea - Response to RFI - December 2023
- Telopea RFI Package Cover Letter - September 2023
- Telopea RFI Response - September 2023
- Telopea Submissions Report
- Telopea_RFI Response_December 2022
Determination9
What's near it
Where it is
- Suburb
- Telopea
- Council area
- Parramatta
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.