A 14,000 tonne a week feedmill at Wallamore Road, Tamworth

Decided: approved on 4 Nov 2026AgricultureNeighbourhood scale

Where it is in the process

Approved on 4 Nov 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination4 Nov 2026 (done)
  9. Approved4 Nov 2026

What it proposes

AI summary. Written from this project's page and its Assessment Report and Instrument of Consent on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 14,000 tonne a week feedmill at Wallamore Road, Tamworth

The proponent proposed a new poultry feedmill at the existing Tangaratta Feedmill site, 771 Wallamore Road, Wallamore, in the Tamworth Regional Council area. After amendment, the new mill is limited to 14,000 tonnes of feed a week. The existing mill stays in use, limited to 2,200 tonnes a week. The department gives an estimated development cost of about $80.9 million, up to 123 construction jobs and 21 operational jobs. It also includes silos, a boiler house, a workshop and an administration building.

The environmental impact statement (EIS) was exhibited from 10 Oct 2024 to 6 Nov 2024. It drew 1 submission, a comment from a public authority. The proponent amended the project, and the department accepted the amendment on 20 Feb 2026. A director of the department, acting for the Minister, approved it on 4 Nov 2026, with conditions. Next, the proponent must meet those conditions before construction and operation.

Capital investment
$80.9MAssessment Report
Construction jobs
123 jobsAssessment Report
Operational jobs
21 jobsAssessment Report
New mill capacity
14,000 tonnes a weekAssessment Report
Existing mill limit
2,200 tonnes a weekAssessment Report
Site area
40.62 haAssessment Report

The department's description

Construction and operation of a feedmill with the capacity to process up to 17,500 tonnes pf poultry feed per week. The new feedmill will incorporate a new milling tower, storage silos, boiler house, maintenance workshop and administration building

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

1 submission: 1 from public authorities

Object0
Support0
Comment1

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

109 documents in 9 folders, each on the NSW Planning Portal

Notice of Exhibition1
Request for SEARs4
SEARs2
EIS29
Response to Submissions2
Agency Advice24
Amendments2
Additional Information42
Determination3

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.