State significant development

Tallawang Solar Farm

Decided: approved on 7 Oct 2025Energy: solarDistrict scale

Where it is in the process

Approved on 7 Oct 2025

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination7 Oct 2025 (done)
  9. Approved7 Oct 2025

What it proposes

The department's description

Development of a 500 MW solar farm with 500MW (1000MWh) battery energy storage system and associated infrastructure

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

56 submissions: 52 from the public, 2 from organisations and 2 from public authorities

Object54
Support2
Comment0

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

Tallawang Solar Farm Modification 2 - Energy Storage IncreaseSSD-23700028-Mod-2

Decided: approved on 23 Sep 2026 by the department (director)

Tallawang Solar Farm Modification 2 Increase Energy Storage Capacity

Its 20 documents

20 documents in 5 folders, each on the NSW Planning Portal

Modification Application4

See the 4 documents on the Planning Portal

Agency Advice4

See the 4 documents on the Planning Portal

Additional Information9

See the 9 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Tallawang Solar Farm Modification 1 - temporary accessSSD-23700028-Mod-1

Decided: approved on 10 Sep 2026 by the department (director)

Provide temporary site access to light and heavy vehicles through a new site access point during pre-construction minor works.

Its 17 documents

17 documents in 5 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Agency Advice3

See the 3 documents on the Planning Portal

Additional Information8

See the 8 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Its point is approximate (the register's own, to about a kilometre), and so are these.

Where it is

Suburb
Goonoo Forest
Council area
Mid-Western Regional

Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0

Other State projects near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.