Decided: approved on 4 Jun 2014Transport

Where it is in the process

Approved on 4 Jun 2014

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination4 Jun 2014 (done)
  9. Approved4 Jun 2014

What it proposes

The department's description

Sydney CBD Light Rail

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

495 submissions: 394 from the public and 101 from organisations

Object232
Support85
Comment178

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

6 changes to the project after its decision, each assessed as a case of its own, newest first.

Sydney CBD Light Rail - Mod 6 - Tree PruningSSI-6042-MOD-6

Decided: approved on 21 Feb 2017 by the Minister

The modification relates to requirements regarding Tree Pruning.

Its 5 documents

5 documents in 4 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

Submissions1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Approval1

See the document on the Planning Portal

Its page on the Planning Portal

Sydney CBD Light Rail - Mod 5 - Randwick Noise MitigationSSI-6042-MOD-5

Decided: approved on 6 Jun 2016 by the department (director)

Transport for NSW is requesting an administrative modification to change the timing requirments of condition of approval B13.

Its 4 documents

4 documents in 2 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Sydney CBD Light Rail - Mod 4 - Stop AmendmentsSSI-6042-MOD-4

Decided: approved on 18 Apr 2016 by the Minister · 115 submissions

- Design changes to the Randwick Terminus and UNSW High Street stop - provision of a new access laneway from Arthur Street to High Street - modification to the local traffic network - revised arrangement of the High Cross Park substation

Its 15 documents

Its page on the Planning Portal

Sydney CBD Light Rail - Mod 3 - Local Access PlansSSI-6042-MOD-3

Decided: approved on 30 Sep 2015 by the department (director)

Request to amend condition B24 in relation to local access plans.

Its 4 documents

4 documents in 3 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

Recommendation1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Sydney CBD Light Rail - Mod 2 - Definition of ConstructionSSI-6042-MOD-2

Decided: approved on 17 Mar 2015 by the department (director)

The modification requests the change of the definition of construction to allow some works to be undertaken as non-construction.

Its 4 documents

4 documents in 2 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Sydney CBD Light Rail - Mod 1 - Design ModificationsSSI-6042-MOD-1

Decided: approved on 17 Feb 2015 by the Minister · 119 submissions

The Proponent proposes a number of design modifications to the approved project.

Its 7 documents

7 documents in 4 folders, each on the NSW Planning Portal

EIS1

See the document on the Planning Portal

Response to Submissions3

See the 3 documents on the Planning Portal

Recommendation1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.