On the map
State significant development

Sport and Wellbeing Centre, Roseville College

Decided: approved on 18 Jun 2021Education

Where it is in the process

Approved on 18 Jun 2021

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination18 Jun 2021 (done)
  9. Approved18 Jun 2021

What it proposes

The department's description

Construction and operation of a new Sport and Wellbeing Centre including basement car parking, swimming pool, gym, learning areas, food technology space, amenities and storage, rooftop sports courts, landscaping, signage and tree removal.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

75 submissions: 67 from the public, 1 from organisations and 7 from public authorities

Object58
Support9
Comment8

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

Sport and Wellbeing Roseville MOD 2 - LandscapingSSD-9912-Mod-2

Decided: approved on 29 Jan 2024 by the department (team leader)

Minor alterations to the forecourt landscaping on the western side of the Sports and Well Being Centre.

Its 12 documents

12 documents in 5 folders, each on the NSW Planning Portal

Modification Application4

See the 4 documents on the Planning Portal

Agency Advice1

See the document on the Planning Portal

Recommendation3

See the 3 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Sport and Wellbeing Centre Rosev MOD 1 - DesignSSD-9912-Mod-1

Decided: approved on 26 May 2022 by the department (director)

Minor design amendments to the approved Sport and Wellbeing Centre and improved landscaping outcomes for the site.

Its 13 documents

13 documents in 5 folders, each on the NSW Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Agency Advice1

See the document on the Planning Portal

Additional Information3

See the 3 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.