Site Verification Certificate – Tomingley Gold Mine
Where it is in the process
Certificate Issued on 7 Dec 2020
What it proposes
The department's description
Extension of the Mine Site boundary to incorporate construction and use of a new Residual Storage Facility (RSF2), and extension of the project life from 31 December 2022 to 31 December 2025.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
2 documents in 2 folders, each on the NSW Planning Portal
Application1
Determination1
What's near it
Where it is
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project
Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.