Signage Pedestrian overbridge, Taverners Hill

Decided: approved on 1 Dec 2008Other

Where it is in the process

Approved on 1 Dec 2008

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination1 Dec 2008 (done)
  10. Approved1 Dec 2008

What it proposes

The portal gives no description.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project