On the map
State significant development

Saint Ignatius' College Riverview Redevelopment Stage 2

Decided: approved on 25 Oct 2021Education

Where it is in the process

Approved on 25 Oct 2021

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination25 Oct 2021 (done)
  9. Approved25 Oct 2021

What it proposes

The department's description

The proposed development seeks built form approval for Stage 2 including the construction of new five (5) storey learning and flexible teaching building and upgrades to a courtyard to include learning space.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

9 submissions: 1 from the public and 8 from public authorities

Object1
Support0
Comment8

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

Saint Ignatius Riverview Stage 2 MOD 1 - LayoutSSD-10424-Mod-1

Decided: approved on 29 Nov 2022 by the department (team leader)

The following amendments have been proposed; re-configuration of Internal layout modify doors and window change multipurpose hall to teaching spaces and modify landscape drawings

Its 13 documents

13 documents in 3 folders, each on the NSW Planning Portal

Modification Application8

See the 8 documents on the Planning Portal

Determination4

See the 4 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.