State significant development

Rix's Creek Coal Mine Extension

Decided: approved on 12 Oct 2019Mining

Where it is in the process

Approved on 12 Oct 2019

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination12 Oct 2019 (done)
  8. Approved12 Oct 2019

What it proposes

The portal gives no description.

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

Rix's Creek South MOD 1 - Condition ErrorsSSD-6300-Mod-1

Decided: approved on 13 Jul 2021 by the department (director)

To allow for the correction of minor condition errors in SSD 6300, enable receipt of limited remnant coalaceous material from other Bloomfield owned sites, and allow for other minor ancillary activities.

Its 11 documents

11 documents in 5 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice5

See the 5 documents on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Its point is approximate (the register's own, to about a kilometre), and so are these.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.