Residential development with in-fill affordable housing - 11-23 Rangers Avenue, Mosman
A 44-apartment building at 11-23 Rangers Avenue, Mosman
Where it is in the process
Approved on 26 Oct 2026
What it proposes
AI summary. Written from this project's page and its SSD Instrument of consent and Signed Assessment Report on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
A 44-apartment building at 11-23 Rangers Avenue, Mosman
The project is a six to seven storey residential flat building at 11-23 Rangers Avenue, Mosman, in the Mosman Municipality. It has 44 apartments, 10 of them affordable housing, over three basement levels with 91 car spaces. The existing houses on the site of 3,594 m² would be demolished. The estimated development cost is $85,135,825, with 124 construction jobs.
The environmental impact statement (EIS) was exhibited from 4 Dec 2025 to 17 Dec 2025. The case drew 182 submissions: 177 objecting, 2 supporting and 3 commenting. The proponent responded to submissions and amended the project, including a final amendment on 16 Oct 2026. The department's assessment recommended approval, and its Deputy Secretary approved it on 26 Oct 2026, as the Minister's delegate, with conditions. Next, the proponent must meet the conditions, including before construction starts.
- Estimated development cost
- $85.1MSigned Assessment Report
- Apartments
- 44 dwellingsSSD Instrument of consent
- Affordable housing apartments
- 10 dwellingsSSD Instrument of consent
- Car spaces
- 91 car spacesSSD Instrument of consent
- Construction jobs
- 124 jobsSigned Assessment Report
- Site area
- 3,594 m²Signed Assessment Report
The department's description
Residential development
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
182 submissions: 178 from the public, 3 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
114 documents in 9 folders, each on the NSW Planning Portal
Early Consultation1
EIS45
- Appendix A-SEARs Requirements Table
- Appendix AA- Survey
- Appendix BB- TIA
- Appendix B_DA Drawing Set
- Appendix C - Statutory Compliance Table (2)
- Appendix CC - Visual Impact Assessment
- Appendix D- Mitigation Measures Table
- Appendix DD_Operational WMP
- Appendix E- Engagement summary table
- Appendix EE - BCA Report
- Appendix FF- Accessibility Report
- Appendix F_Aboriginal Due Diligence Report
- Appendix G--Prelim Site Investigation
- Appendix GG_Surveyor Walking Map
- Appendix H- Arboricultural Impact Assessment
- Appendix HH_ Design Verification Statement
- Appendix II-Integrated SW Mgmt Plan
- Appendix I_BASIX
- Appendix J-BDAR Waiver Determination
- Appendix J_BDAR Waiver
- Appendix K_Community Housing Provider Letter
- Appendix L - Clause 4.6 Variation Request_Building Height
- Appendix L_Clause 4.6 Variation Request_Wall Height
- Appendix M_ Design Report Part 1
- Appendix M_ Design Report Part 2
- Appendix M_ Design Report Part 3
- Appendix M_ Design Report Part 4
- Appendix N-DWMP
- Appendix O-EDC Letter
- Appendix P -Engagement Outcomes Report
- Appendix Q- ESD Report Part 2
- Appendix Q- ESD Report Part 3
- Appendix Q-ESD Report Part 1
- Appendix Q-ESD Report Part 4
- Appendix R- Flood Impact Risk Assessment
- Appendix S-Geotechnical
- Appendix T- Integrated SW Mgmt Plan
- Appendix U-Landscape Concept
- Appendix V- Noise and Vibration Report
- Appendix W_Construction Traffic Management Plan
- Appendix X- DWMP
- Appendix Y -Social Impact Assessment
- Appendix Z -HIS
- Application_20251124034222
- Environmental Impact Statement
Exhibition1
Response to Submissions23
- Appendix A - Summary Response Table
- Appendix B_Mitigation Measures Table
- Appendix C - Statutory Compliance Table - Updated
- Appendix D_Design Verification Statement
- Appendix E _Rangers_Ave_Drawing_Set
- Appendix F_Rangers Avenue_ADG_Checklist
- Appendix G_Stormwater Plan
- Appendix H_Letter of Response to Stormwater Comments
- Appendix I_Letter of Response to Flooding Comments
- Appendix J_Letter to Traffic Impact Assessment
- Appendix L_Updated Operational Waste Management Plan
- Appendix M_ Landscape Plans
- Appendix N_Geotechnical Investigation
- Appendix O_Letter to Heritage Impact Statement
- Appendix P_BCAStatement
- Appendix S_Updated Engagement Report
- Appendix T_Updated Preliminary Site Investigation
- Appendix U_Updated Hydrogeological Report
- Appendix V_ELAB_BASIX_13-23 Rangers Ave_02
- Appendix_K_VIA
- Clause 4.6 Variation Request_Building Height
- Request RTS Letter
- Response to Submissions_Report
Agency Advice3
Additional Information32
- 0726_SurveyorReport_RFI
- 0726_Traffic_RFI
- 11-23Rangers_RFI_Geotech_Signed_Letter
- 11-23_Rangers_Avenue_Geotech_DesignCompliance
- 11_23 Rangers Avenue Mosman RTS_Transport
- 11_23_Rangers-Avenue_Geotech_Report
- 11_23_Rangers_Avenue_Engineer_Qualifications
- 11_23_Rangers_Avenue_Flooding
- 11_23_Rangers_Avenue_Response to DPHI Comments_Stormwater
- 11_23_Rangers_Avenue_Traffic_Base_Count
- Add info letter 9.09
- Additional Information - 30 September 2026
- Architecture Plans- 9.09
- DA5001
- DA7120
- DA7121
- DA7122
- DA7130
- Final Cl 4.6 _ Wall Height 9.09
- Flood Response Letter 9.09
- Land Risk Assessment Checklist 9.09
- Public Transport memo 9.09
- RFI_Letter_Urbis_170826
- RFI_Letter_WoodsBagot_Overshadowing_JF_130826
- Request for Additional Information
- SK7001
- Shadow Analysis 9.09
- Signed Key Issues letter
- Traffic Letter 9.09
- Updated Traffic Volume- Spofforth St -17.09.26
- Updated walking distance survey map 17.09.26
- Waste collection info 9.09
What's near it
Where it is
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.