On the map
State significant development

Residential Development with affordable housing - Florence Street, Tweed Heads

A 13-storey tower with 59 homes at Florence Street, Tweed Heads

Decided: approved on 25 Jun 2026HomesNeighbourhood scale

Where it is in the process

Approved on 25 Jun 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination25 Jun 2026 (done)
  9. Approved25 Jun 2026

What it proposes

AI summary. Written from this project's page and its SSD Assessment Report and SSD Instrument of Consent on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 13-storey tower with 59 homes at Florence Street, Tweed Heads

The project is a 13-storey residential tower at 12-16 Florence Street, Tweed Heads, in the Tweed Shire Council area. It has 59 dwellings, including 12 affordable housing units, with a gross floor area of 6,582.4 m² and a height of 44.1 m. It includes 2 basement levels and 71 car spaces on a site of 1558 m². The estimated development cost is $38,869,296, with 80 construction jobs.

The environmental impact statement (EIS) was exhibited from 19 Nov 2025 to 2 Dec 2025 and drew 15 submissions: 11 objecting, 1 supporting and 3 commenting. The proponent responded in April 2026. The department found the key issues were built form, building separation, overshadowing and flooding, and recommended approval. A director of the department, acting for the Minister, approved it on 25 Jun 2026, with conditions. Next, the proponent must meet those conditions before and during construction.

Estimated development cost
$38.9MSSD Assessment Report
Dwellings
59 dwellingsSSD Instrument of Consent
Affordable housing units
12 dwellingsSSD Instrument of Consent
Storeys
13 storeysSSD Instrument of Consent
Building height
44.1 mSSD Assessment Report
Maximum gross floor area
6,582.4 m²SSD Instrument of Consent
Construction jobs
80 jobsSSD Assessment Report
Car parking spaces
71 car spacesSSD Assessment Report

The department's description

Residential flat building with affordable housing

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

15 submissions: 14 from the public and 1 from public authorities

Object11
Support1
Comment3

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

88 documents in 9 folders, each on the NSW Planning Portal

Early Consultation4
Notice of Exhibition1
Request for SEARs2
SEARs2
EIS39
Response to Submissions12
Agency Advice4
Additional Information15
Determination9

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.