State significant development

Rasp Lead/Zinc/Silver Project

Decided: approved on 31 Jan 2011Mining

Where it is in the process

Approved on 31 Jan 2011

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination31 Jan 2011 (done)
  8. Approved31 Jan 2011

What it proposes

The department's description

To develop an underground mine and associated infrastructure to extract 750,000 tonnes of ore per year until 2026, and transport ore concentrate by rail to Port Pirie in SA and Newcastle in NSW.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Modifications

13 changes to the project after its decision, each assessed as a case of its own, newest first.

Rasp MOD 13 - Various, including approval extensionMP07_0018-Mod-13

Decided: approved on 22 Sep 2026 by the department (director) · 3 submissions

Extend underground mining within the CML7 and mine life by 5 years, receipt and processing of Pinnacles Mine ore, other infrastructure changes, including a new emergency egress ladder, a filtration plant on a free area, a tailings dewatering system.

Its 25 documents

25 documents in 8 folders, each on the NSW Planning Portal

Early Consultation1

See the document on the Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application3

See the 3 documents on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Agency Advice7

See the 7 documents on the Planning Portal

Additional Information7

See the 7 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 12 - Underground Mining ExtensionMP07_0018-Mod-12

Decided: approved on 18 Nov 2025 by the department (director) · 1 submission

To extend underground mining activities in Main Lode (ML) Blocks 13, 14, 15 and 16.

Its 19 documents

19 documents in 8 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Early Consultation1

See the document on the Planning Portal

Modification Application4

See the 4 documents on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Agency Advice6

See the 6 documents on the Planning Portal

Additional Information1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 11 - Ventilation Intake and Underground ExplorationMP07_0018-Mod-11

Decided: approved on 15 Mar 2024 by the department (director)

To install and use a new ventilation intake and further extend underground exploration in the Main Lode to Blocks 13 - 15 within the current Mining Lease (CML7).

Its 14 documents

14 documents in 5 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice5

See the 5 documents on the Planning Portal

Additional Information5

See the 5 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 10 - Temporary tailings placement in TSF2MP07_0018-Mod-10

Decided: approved on 13 Dec 2022 by the department (director)

Construction of a new intake vent and temporary placement of dried tailings in the tailings storage facility

Its 7 documents

7 documents in 4 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice3

See the 3 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 6 – New Tailing Storage FacilityMP07_0018-Mod-6

Decided: approved on 16 Mar 2022 by the department (director) · 2 submissions

To use the Kintore Pit a a new tailing storage facility (TSF3), relocate the current mine portal, provide for future waste rock emplacement areas (currently stored in Kintore Pit), and provide for associated service facilities..

Its 60 documents

Its page on the Planning Portal

MOD 9 - Extension of Underground ExplorationMP07_0018-Mod-9

Decided: approved on 23 Dec 2021 by the department (director)

To extend underground exploration in the Main Lode to Blocks 13 - 15 within the current Mining Lease (CML7), and install an emergency egress ladder way from Stockpile 1 (SP1) underground to the surface

Its 11 documents

11 documents in 5 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice5

See the 5 documents on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

MOD 8 - Mining ExtensionMP07_0018-Mod-8

Decided: approved on 15 Apr 2021 by the department (director)

To extend underground mining across the project’s CML7 to mine a predefined region of ML1249 under a sub-lease arrangement with Perilya Broken Hill Limited (Southern Operations).

Its 4 documents

4 documents in 3 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

MOD7 - Additional Crushing and ScreeningMP07_0018-Mod-7

Decided: approved on 29 Jul 2019 by the department (director)

To utilise rock fill material stored in BHP Pit for Blackwood Pit (TSF2) embankment construction; and conduct crushing and screen activities within BHP Pit

Its 10 documents

10 documents in 3 folders, each on the NSW Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Determination4

See the 4 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Rasp Mine MOD5 - Cement Transportation and StorageMP07_0018-Mod-5

Decided: approved on 2 Nov 2018 by the department (director)

To construct a cement silo, import 5,000 tonnes of cement to the site, extend an existing warehouse and update the mine’s air quality monitoring requirements to be consistent with the Environment Protection Licence.

Its 18 documents

Its page on the Planning Portal

Rasp Mine MOD4 - Tailings Storage Pit Capacity IncreaseMP07_0018-Mod-4

Decided: approved on 6 Sep 2017 by the department (executive director) · 9 submissions

To increase the Blackwood Pit (TSF2) capacity from 4 to 5 million tonnes by constructing 3 embankments and a retaining wall at low points along the pit rim, and constructing an on-site concrete batching plant.

Its 24 documents

Its page on the Planning Portal

Rasp Mine MOD3 - Underground Mining ExpansionMP07_0018-Mod-3

Decided: approved on 17 Mar 2015 by the department (executive director)

To expand underground mining operations into Block 7 (south west of the site) over 2 to 3 years using progressive mining methods, and install 4 new ventilation fan in Block 7.

Its 26 documents

Its page on the Planning Portal

Rasp Mine MOD 2 - Ore Crushing Operating HoursMP07_0018-Mod-2

Decided: approved on 29 Aug 2014 by the department (executive director) · 1 submission

To increase the approved ore crushing operating hours to 24 hours a day.

Its 15 documents

Its page on the Planning Portal

MOD 1 - Ventilation Rise RelocationMP07_0018-Mod-1

Decided: approved on 16 Mar 2012 by the department (executive director)

Relocation of the ventilation rise from the Little Kintore pit (as approved) to the north-western side of the CML7 lease.

Its 14 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.