On the map
State significant development

Quorn Park Solar Farm

Decided: approved on 16 Jul 2020Other

Where it is in the process

Approved on 16 Jul 2020

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination16 Jul 2020 (done)
  9. Approved16 Jul 2020

What it proposes

The department's description

Development of a 80 MW solar farm, associated infrastructure and potential battery storage.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

52 submissions: 41 from the public and 11 from public authorities

Object40
Support1
Comment11

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

Quorn Park Modification 2 - Intersection upgrade modificationSSD-9097-Mod-2

Decided: approved on 10 Dec 2024 by the department (director)

Modification of the consent to change the impact footprint for the approved road upgrade works at the intersection of Henry Parkes Way and McGrath Lane.

Its 19 documents

19 documents in 5 folders, each on the NSW Planning Portal

Modification Application4

See the 4 documents on the Planning Portal

Agency Advice8

See the 8 documents on the Planning Portal

Additional Information4

See the 4 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Quorn Park Modification 1 - BESS durationSSD-9097-Mod-1

Decided: approved on 7 Jun 2024 by the department (director)

An increase in the battery energy storage system duration from 1 hour to 2 hour, and an increase in the number of inverters from 19 to 22

Its 9 documents

9 documents in 3 folders, each on the NSW Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.