On the map
State significant infrastructure

Queensland-Hunter Gas Pipeline

Decided: approved on 11 Feb 2009Energy: other

Where it is in the process

Approved on 11 Feb 2009

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination11 Feb 2009 (done)
  8. Approved11 Feb 2009

What it proposes

The department's description

Queensland-Hunter Gas Pipeline

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Modifications

1 change to the project after its decision, each assessed as a case of its own, newest first.

MOD 1 - Lapse Date ExtensionMP06_0286-Mod-1

Decided: approved on 17 Oct 2019 by the Minister · 194 submissions

Extension of Project Approval lapse date

Its 18 documents

18 documents in 6 folders, each on the NSW Planning Portal

Application2

See the 2 documents on the Planning Portal

Modification Application7

See the 7 documents on the Planning Portal

Response to Submissions1

See the document on the Planning Portal

Additional Information4

See the 4 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Approval1

See the document on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.