On the map
State significant development

Project Apollo Data Centre Macquarie Park

A 135 MW data centre at Talavera Road, Macquarie Park

Decided: approved on 2 Sep 2026Data centresRegional scale

Where it is in the process

Approved on 2 Sep 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination2 Sep 2026 (done)
  9. Approved2 Sep 2026

What it proposes

AI summary. Written from this project's page and its Project Apollo DC - Assessment Report and Project Apollo DC - Development Consent on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 135 MW data centre at Talavera Road, Macquarie Park

The project is a data centre at 4-10 Talavera Road, Macquarie Park, in the City of Ryde. It would replace two warehouse buildings with a data centre of up to 45 m, with eight data halls and a total power demand of up to 135 MW. It would have 66 back-up diesel generators and 36 evaporative cooling towers. The estimated development cost is $1.365 billion, with up to 400 construction jobs and 60 operational jobs.

The environmental impact statement (EIS) was exhibited from 21 Mar 2025 to 17 Apr 2025. There were no public submissions; the council objected, mainly over urban design, and 1 submission was counted. The proponent responded with a submissions report. The department's assessment focused on operational noise and urban design and found the impacts acceptable. An Acting Director of the department, as the Minister's delegate, approved it on 2 Sep 2026, with conditions. Next, the proponent must meet those conditions.

Estimated development cost
$1.37bnProject Apollo DC - Assessment Report
Maximum power consumption
135 MWProject Apollo DC - Assessment Report
Maximum building height
45 mProject Apollo DC - Assessment Report
Construction jobs
400 jobsProject Apollo DC - Assessment Report
Operational jobs
60 jobsProject Apollo DC - Assessment Report
Back-up diesel generators
66 generatorsProject Apollo DC - Assessment Report
Gross floor area
28,878 m²Project Apollo DC - Assessment Report

The department's description

Construction, fit out and 24/7 operation of a Data Centre including ancillary office space with an initial load capacity of approximately 90MVA and associated carparking and landscaping.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

1 submission: 1 from public authorities

Object1
Support0
Comment0

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

104 documents in 9 folders, each on the NSW Planning Portal

Early Consultation1
Notice of Exhibition1
Request for SEARs2
SEARs2
EIS41
Response to Submissions31
Agency Advice17
Additional Information2
Determination7

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.