On the map
Part 4 development

Precinct A, Rhodes - 229 Res Units, Shops

Decided: approved on 9 Sep 2003Mixed use

Where it is in the process

Approved on 9 Sep 2003

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination9 Sep 2003 (done)
  10. Approved9 Sep 2003

What it proposes

The portal gives no description.

Modifications

4 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 4 - Administrative ChangeDA99-3-2003-Mod-4

Decided: approved on 23 Aug 2006 by the Minister

Its page on the Planning Portal

Mod 2 - Amend condition E8DA99-3-2003-Mod-2

Decided: approved on 16 Nov 2005 by the Minister

Its 2 documents

2 documents in 1 folder, each on the NSW Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 1 - To amend cond D6DA99-3-2003-Mod-1

Decided: approved on 16 Nov 2005 by the Minister

Its 2 documents

2 documents in 1 folder, each on the NSW Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 3 - Correction of S94 ContributionsDA99-3-2003-Mod-3

Decided: approved on 4 Dec 2003 by the Minister

Its 2 documents

2 documents in 1 folder, each on the NSW Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

2 documents in 1 folder, each on the NSW Planning Portal

Determination2

See the 2 documents on the Planning Portal

What's near it

Its point is approximate (the register's own, to about a kilometre), and so are these.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.