On the map
Part 3A project

Port Kembla Steelworks - Cogeneration Plant

Cogeneration plant at the Port Kembla Steelworks

Decided: approved on 15 Dec 2008Industry and warehousesNeighbourhood scale

Where it is in the process

Approved on 15 Dec 2008

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination15 Dec 2008 (done)
  10. Approved15 Dec 2008

What it proposes

AI summary. Written from this project's page and its Director-General's Assessment Report.pdf and Minister's Approval.pdf on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

Cogeneration plant at the Port Kembla Steelworks

The project is a cogeneration plant at the Port Kembla Steelworks on Five Islands Road, Port Kembla, in the Wollongong City Council area. The portal gives no description, and no capacity, capital investment or job numbers are stated in the information available, so the size of the plant is not known.

It was assessed under the former Part 3A process. The Director-General's environmental assessment requirements were issued, and the proponent lodged a project application. The Director-General's assessment report went to the Minister. The Minister approved the project on 15 Dec 2008. No public submissions are recorded. Next, the proponent must meet the conditions of approval, and the project may later be modified.

The portal gives no description.

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 2 - Interim ProjectMP08_0132-Mod-2

Decided: approved on 9 Jul 2010 by the department (executive director)

Its 3 documents

3 documents in 2 folders, each on the NSW Planning Portal

EA1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 1 - Design ChangesMP08_0132-Mod-1

Decided: approved on 15 Dec 2008 by the Minister

Its 38 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

5 documents in 4 folders, each on the NSW Planning Portal

Request for DGRS1
Application1
Determination2
Reports1

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.