A 500 MW battery at Brays Lane, Lidsdale

Under way: at exhibitionEnergy: batteriesDistrict scale

Where it is in the process

At exhibition, since 4 Nov 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition4 Nov 2026 (current stage)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

Open for comment until 2 Dec 2026. Anyone can make a submission on its page on the Planning Portal.

What it proposes

AI summary. Written from this project's page and its EIS on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 500 MW battery at Brays Lane, Lidsdale

The proponent proposes to build, operate and later decommission a battery energy storage system of up to 500 MW and 1,000 MWh (two-hour duration) at 257 Brays Lane, Lidsdale, in the Lithgow City Council area. It would be known as the Pinecrest BESS. The project also includes ancillary infrastructure such as underground cabling, a transmission line, an acoustic barrier and vegetation screening. No capital investment or job numbers are stated.

The environmental impact statement (EIS) is on public exhibition from 4 Nov 2026 to 2 Dec 2026, and no submissions have been recorded yet. Next, the proponent responds to the submissions and may amend the project. The department then assesses it, with advice from other agencies, and writes an assessment report. The department or the Independent Planning Commission then decides.

Battery power capacity
500 MWEIS
Battery storage capacity
1,000 MWhEIS

The department's description

Construction, operation, and decommissioning of a battery energy storage system (BESS) with a capacity of 500 MW/1000 MWh and ancillary infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.