On the map
Part 3A project

Pacific Highway - Banora Point

Decided: approved on 26 Feb 2009Transport

Where it is in the process

Approved on 26 Feb 2009

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination26 Feb 2009 (done)
  10. Approved26 Feb 2009

What it proposes

The portal gives no description.

Modifications

6 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 3 - Urban Design + LandscapingMP07_0059-Mod-3

Withdrawn: withdrawn

Its page on the Planning Portal

Mod 6 - Operational ManagementMP07_0059-Mod-6

Decided: approved with conditions on 28 Sep 2012 by Dir(MIA)

Its 5 documents

5 documents in 2 folders, each on the NSW Planning Portal

Application2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Mod 5 - Construction HoursMP07_0059-Mod-5

Decided: approved on 17 May 2012 by Dir(MIA)

Its 7 documents

Its page on the Planning Portal

Mod 4 - Blasting LimitsMP07_0059-Mod-4

Decided: approved on 12 Apr 2011 by Dir(MIA)

Its 13 documents

13 documents in 2 folders, each on the NSW Planning Portal

Application10

See the 10 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Its page on the Planning Portal

Mod 2 - Staging ChangesMP07_0059-Mod-2

Decided: approved on 19 Nov 2009 by the department (executive director)

Its 5 documents

5 documents in 2 folders, each on the NSW Planning Portal

Application3

See the 3 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Mod 1 - Stakeholder ConsultationsMP07_0059-Mod-1

Decided: approved on 15 Oct 2009 by the department (executive director)

Its 4 documents

4 documents in 2 folders, each on the NSW Planning Portal

Application2

See the 2 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

11 documents in 4 folders, each on the NSW Planning Portal

Application6

See the 6 documents on the Planning Portal

Request for DGRS1

See the document on the Planning Portal

Response to Submissions1

See the document on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.