OneSteel Steel Mill

Decided: decidedIndustry and warehouses

Where it is in the process

At determination

  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination (current stage)

What it proposes

The department's description

OneSteel Steel Mill

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Modifications

9 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 1 - OneSteel Steel MillDA11/94-Mod-1

Decided: approved by the Minister

Its page on the Planning Portal

Sydney Steel Mill MOD 9 - PCT CorrectionDA11/94-Mod-9

Decided: approved on 4 Mar 2025 by the department (team leader)

Correction of reference to Plant Community Type (PCT) 3320 in Schedule 3, Condition 63A of the modified consent.

Its 4 documents

4 documents in 3 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Sydney Steel Mill MOD 8 - SATCOMDA11/94-Mod-8

Decided: approved on 27 Nov 2024 by the department (team leader)

Modification to install Static Synchronous Compensator and move office building.

Its 17 documents

17 documents in 5 folders, each on the NSW Planning Portal

Modification Application2

See the 2 documents on the Planning Portal

Agency Advice6

See the 6 documents on the Planning Portal

Additional Information6

See the 6 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Sydney Steel Mill MOD 7 - Tank InstallationDA11/94-Mod-7

Decided: approved on 19 Oct 2023 by the department (team leader)

Installation of an underground tank and associated infrastructure to capture water and spills from existing transformers.

Its 8 documents

8 documents in 6 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice2

See the 2 documents on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Recommendation1

See the document on the Planning Portal

Determination1

See the document on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Sydney Steel Mill MOD 6 - Storage and Transformer ChangesDA11/94-Mod-6

Decided: approved on 9 Dec 2021 by the department (team leader)

Use of existing bunker for the storage of allows and the construction of two transformer storage bunds.

Its 13 documents

13 documents in 5 folders, each on the NSW Planning Portal

Modification Application1

See the document on the Planning Portal

Agency Advice6

See the 6 documents on the Planning Portal

Additional Information2

See the 2 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Mod 5 - Rolling Mill IncreaseDA11/94-Mod-5

Decided: approved on 29 Oct 2015 by the Independent Planning Commission

Its 14 documents

Its page on the Planning Portal

Mod 4 - Increase in Production RateDA11/94-Mod-4

Decided: approved on 19 Sep 2008 by the department (executive director)

Its 1 documents

1 document in 1 folder, each on the NSW Planning Portal

Assessment1

See the document on the Planning Portal

Its page on the Planning Portal

Mod 3 - Alternate Carbon InjectantsDA11/94-Mod-3

Decided: approved on 21 May 2008 by the Minister

Its page on the Planning Portal

Mod 2 - OneSteel Steel MillDA11/94-Mod-2

Decided: decided on 15 Sep 2005 by the department (director)

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

11 documents in 2 folders, each on the NSW Planning Portal

Management Plans and Strategies9

See the 9 documents on the Planning Portal

Reports2

See the 2 documents on the Planning Portal