On the map
State significant development

NEXTDC S4 Data Centre Horsley Park

A 294 MW data centre at 16 Johnston Crescent, Horsley Park

Decided: approved on 24 Dec 2025Data centresRegional scale

Where it is in the process

Approved on 24 Dec 2025

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination24 Dec 2025 (done)
  9. Approved24 Dec 2025

What it proposes

AI summary. Written from this project's page and its Signed - SSD Instrument of Consent and Signed - SSD-SSI Assessment Report on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 294 MW data centre at 16 Johnston Crescent, Horsley Park

The project is a data centre campus at 16 Johnston Crescent, Horsley Park, in the Fairfield City and Blacktown council areas. It has two four-storey data centre buildings with a total capacity of 294 MW, and two 330kV transmission lines about 2.6 km long to the TransGrid Sydney West Substation. The department gives an estimated development cost of 3.1 billion and the main site is 8.206 ha. The proponent amended the project after exhibition, cutting five buildings to two.

The environmental impact statement (EIS) was exhibited from 26 Jul 2024 to 22 Aug 2024. The amended application was exhibited from 18 Sep 2025 to 1 Oct 2025. The portal counts 7 submissions: 3 objecting, 1 supporting and 3 commenting. The department found the project approvable, and its Executive Director approved it on 24 Dec 2025, as the Minister's delegate, with conditions. Next, the proponent must meet those conditions, including noise limits, before and during construction.

Estimated development cost
$3.1bnSigned - SSD-SSI Assessment Report
Data centre capacity
294 MWSigned - SSD-SSI Assessment Report
Data centre buildings
2 buildingsSigned - SSD-SSI Assessment Report
Transmission line length
2.6 kmSigned - SSD-SSI Assessment Report
Main site area
8.21 haSigned - SSD-SSI Assessment Report
Gross floor area
61,695 m²Signed - SSD-SSI Assessment Report
Maximum building height
38 mPortal page

The department's description

Construction and operation of a data centre comprising of six data centre buildings with a maximum height of 38 m and an operational capacity of 250 MW, including substation, earthworks, car parking, landscaping and ancillary works.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

7 submissions: 5 from the public, 1 from organisations and 1 from public authorities

Object3
Support1
Comment3

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

NEXTDC S4 Horsley Park MOD 2 - Acoustic Barrier AmendmentsSSD-63741210-Mod-2

Decided: approved on 23 Sep 2026 by the department (team leader)

Increase in height of transformer noise wall and an increase in height and length of HVSB noise wall.

Its 7 documents

7 documents in 3 folders, each on the NSW Planning Portal

Modification Application4

See the 4 documents on the Planning Portal

Agency Advice1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

NEXTDC S4 Modification 1 - Design ModificationsSSD-63741210-Mod-1

Decided: approved on 7 Aug 2026 by the department (team leader)

Increase to the size of pump house and fire bump buildings, increase in heigh of water tanks, amendments to acoustic walls including new acoustic wall, increase in bulk fuel capacity and minor changes to site landscaping.

Its 21 documents

21 documents in 4 folders, each on the NSW Planning Portal

Modification Application5

See the 5 documents on the Planning Portal

Agency Advice6

See the 6 documents on the Planning Portal

Additional Information8

See the 8 documents on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

147 documents in 11 folders, each on the NSW Planning Portal

Early Consultation3
Notice of Exhibition2
Request for SEARs1
SEARs2
EIS41
Response to Submissions6
Agency Advice23
Amendments51
Determination7
Management Plans and Strategies2
Other Documents9

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.