On the map
State significant development

Nevertire Solar Farm

Decided: approved on 5 Jul 2017Other

Where it is in the process

Approved on 5 Jul 2017

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Assessment (done)
  6. Recommendation (done)
  7. Determination5 Jul 2017 (done)
  8. Approved5 Jul 2017

What it proposes

The department's description

Development of a 105 MW solar farm and associated infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

7 submissions: 2 from the public and 5 from organisations

Object2
Support0
Comment5

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Modifications

4 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 4 Battery Energy Storage SystemSSD-8072-Mod-4

Decided: approved on 29 Jul 2022 by the department (director) · 1 submission

Addition of a 50 MW /100 MWh battery energy storage system

Its 37 documents

37 documents in 7 folders, each on the NSW Planning Portal

Notice of Exhibition1

See the document on the Planning Portal

Modification Application14

See the 14 documents on the Planning Portal

Response to Submissions2

See the 2 documents on the Planning Portal

Agency Advice12

See the 12 documents on the Planning Portal

Additional Information4

See the 4 documents on the Planning Portal

Determination3

See the 3 documents on the Planning Portal

Consolidated Consent1

See the document on the Planning Portal

Its page on the Planning Portal

Nevertire Solar MOD 3 - Temporary AccessSSD-8072-MOD-3

Decided: approved on 22 Nov 2018 by the department (director)

Proposed modification for the use of a separate adjoining lot for the purpose of temporary access and parking for light vehicles during project construction.

Its 4 documents

4 documents in 3 folders, each on the NSW Planning Portal

Application1

See the document on the Planning Portal

Recommendation1

See the document on the Planning Portal

Determination2

See the 2 documents on the Planning Portal

Its page on the Planning Portal

Nevertire Solar MOD 2 - Layout ChangesSSD-8072-MOD-2

Decided: approved on 7 May 2018 by the department (director)

Amendment of the location of the project’s substation, maintenance building and staff amenities infrastructure, and to subdivide the project site.

Its 5 documents

Its page on the Planning Portal

Nevertire Solar MOD 1 - Farm FootprintSSD-8072-MOD-1

Decided: approved on 13 Oct 2017 by the department (director)

Extension of development footprint.

Its 5 documents

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Where it is

Suburb
Nevertire
Council area
Warren

Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.