On the map
State significant development

Murray Terminal BESS

A 500 MW battery at 45 Waterfall Farm Road, Khancoban

Under way: at prepare eisEnergy: batteriesRegional scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 500 MW battery at 45 Waterfall Farm Road, Khancoban

The proponent proposes to build and operate a battery energy storage system with a capacity of approximately 500 MW and 2,000 MWh (four hours of storage), at 45 Waterfall Farm Road, Khancoban, about 4 km south-east of Khancoban in the Snowy Valleys Council area. A 10 ha area has been identified for the battery, with a further 5 ha being looked at for the grid connection and road works. It would connect to the nearby Murray Terminal 330 kV switching station, likely underground. No capital investment is stated.

The case is at the stage where the proponent prepares an environmental impact statement (EIS). The scoping report is dated August 2025, and the Secretary's environmental assessment requirements (SEARs) have been issued. Next, the EIS is to be exhibited, when the public can make submissions. No submissions have been made yet.

Battery power capacity
500 MWScoping Report
Battery storage capacity
2,000 MWhScoping Report
Battery site area
10 haScoping Report
Area for grid connection and road works
5 haScoping Report

The department's description

Construction, operation and decommissioning of a battery energy storage system (BESS) of up to 500 Megawatts (MW) / 2000 MW hour capacity and ancillary infrastructure.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Where it is

Suburb
Khancoban
Council area
Snowy Valleys

Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.