On the map
State significant development

Moss Vale Resource Recovery Facility

A 200,000 tonne a year resource recovery facility, Moss Vale

Under way: at prepare eisWasteLocal scale

Where it is in the process

At prepare eis

  1. SEARs (done)
  2. Prepare EIS (current stage)
  3. Exhibition (to come)
  4. Collate Submissions (to come)
  5. Response to Submissions (to come)
  6. Assessment (to come)
  7. Recommendation (to come)
  8. Determination (to come)

What it proposes

AI summary. Written from this project's page and its 1. JEP Pty Ltd - Purple Cow - Moss Vale - Scoping Report on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

A 200,000 tonne a year resource recovery facility, Moss Vale

The proponent proposes a resource recovery facility at 2 Bowman Road, Moss Vale, in the Wingecarribee Shire. It would receive up to 200,000 tonnes a year of household clean-up, business, and construction and demolition waste, plus waste tyres. It would include a community recycling centre, a sorting and processing area, and a tyre recycling plant of 10,000 tonnes a year. A car park for up to 32 cars, truck parking and skip bin storage are also proposed. The scoping report gives a construction cost of $30 million, up to 20 construction jobs and up to 50 permanent jobs.

The case is at the stage where the proponent prepares an environmental impact statement (EIS). No submissions have been made yet. Next, the EIS is exhibited and the public can make submissions. The proponent then responds, and the department assesses the project. The scoping report says the Independent Planning Commission would be the consent authority.

Waste received
200,000 tonnes a year1. JEP Pty Ltd - Purple Cow - Moss Vale - Scoping Report
Tyre recycling capacity
10,000 tonnes a year1. JEP Pty Ltd - Purple Cow - Moss Vale - Scoping Report
Construction cost
$30M1. JEP Pty Ltd - Purple Cow - Moss Vale - Scoping Report
Construction jobs
20 jobs1. JEP Pty Ltd - Purple Cow - Moss Vale - Scoping Report
Permanent jobs
50 jobs1. JEP Pty Ltd - Purple Cow - Moss Vale - Scoping Report
Car parking spaces
32 car spaces1. JEP Pty Ltd - Purple Cow - Moss Vale - Scoping Report

The department's description

Construction and operation of a resource recovery facility receiving up to 200,000 tonnes per year of commercial and industrial, construction and demolition, household clean-up and tyre waste, including an office, car park and truck/skip bin storage.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 19 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.