  1. Prepare Scoping Report (done)
  2. SEARs (done)
  3. Prepare EIS (done)
  4. Exhibition (done)
  5. Collate Submissions (done)
  6. Response to Submissions (done)
  7. Assessment (done)
  8. Recommendation (done)
  9. Determination30 Nov 2006 (done)
  10. Approved30 Nov 2006

What it proposes

The department's description

Moonee Beach Subdivision

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Modifications

2 changes to the project after its decision, each assessed as a case of its own, newest first.

Mod 1 - Moonee Beach SubdivisionDA148-6-2005-Mod-1

Decided: approved by the department (executive director)

Its page on the Planning Portal

Mod 2 - Moonee Beach SubdivisionDA148-6-2005-Mod-2

Decided: approved on 8 Apr 2008 by the department (executive director)

Its page on the Planning Portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

2 documents in 1 folder, each on the NSW Planning Portal

Determination2

See the 2 documents on the Planning Portal

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 17 Nov 2026. See it on the map · Every State project

Category: Bowerbird's, from the register's development type, in five levels from minor to regional. Its stage is the portal's on the day it was read.