Mixed-Use Precinct with In-Fill Affordable Housing – Hughes Avenue, Melrose Park South-West
1,375 apartments at 82 Hughes Avenue, Ermington
Where it is in the process
Approved on 30 Jun 2026
What it proposes
AI summary. Written from this project's page and its SSD-71558711 - Assessment Report and SSD-71558711 - Instrument of Consent on the NSW Planning Portal, on 19 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
1,375 apartments at 82 Hughes Avenue, Ermington
The project is a mixed-use precinct at 82 Hughes Avenue, Ermington, in the City of Parramatta, on a site of 52,100 m² beside Ermington Bay. It has 12 buildings from 7 to 29 storeys, containing 1,375 apartments, 210 of them affordable, with neighbourhood shops, basement parking and a new public park. The estimated development cost is $641,283,425, and the assessment report gives 269 construction jobs and 125 operational jobs.
The environmental impact statement (EIS) was exhibited from 15 Jul 2025 to 11 Aug 2025. The portal counts 15 submissions: 8 objecting, 2 supporting and 5 commenting. The proponent responded on 12 Mar 2026 and gave more information on 1 May 2026 and 29 Jun 2026. The department recommended approval, and its Director, as the Minister's delegate, approved the project on 30 Jun 2026, with conditions. Next, the proponent must meet those conditions before and during construction.
- Estimated development cost
- $641.3MSSD-71558711 - Assessment Report
- Apartments
- 1,375 dwellingsSSD-71558711 - Instrument of Consent
- Affordable apartments
- 210 dwellingsSSD-71558711 - Instrument of Consent
- Construction jobs
- 269 jobsSSD-71558711 - Assessment Report
- Operational jobs
- 125 jobsSSD-71558711 - Assessment Report
- Tallest building
- 29 storeysSSD-71558711 - Instrument of Consent
- Maximum building height
- 97.78 mSSD-71558711 - Assessment Report
- Public park
- 14,981 m²SSD-71558711 - Assessment Report
The department's description
Construction of a mixed-use development comprising approximately 118,919sqm, basement carparking and servicing, and landscaping and construction of one new waterfront park.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
15 submissions: 11 from the public, 3 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Modifications
1 change to the project after its decision, each assessed as a case of its own, newest first.
Melrose Park South-West - Modification 1SSD-71558711-Mod-1
Section 4.55(1) modification application to amend conditions A15-A18 (timing of HPC payment) and Condition E11 (works-as-executed plans) and deletion of Condition E39 (Council access to loading dock).
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
160 documents in 10 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs4
SEARs2
EIS64
- A10_Biodiversity Development Assessment Report_MPS WEST
- A11_Construction Traffic Management Plan_MPS WEST
- A12_CPTED Assessment_MPS WEST
- A13_ESD Report_MPS WEST
- A14_BASIX Report B1_MPS WEST
- A14_BASIX Report B2_MPS WEST
- A14_BASIX Report B3_MPS WEST
- A15_Thermal Comfort Assessment_MPS WEST
- A16_Melrose Park South-West EDC Summary
- A17_Economic Impact Assessment_MPS WEST
- A18_Flood Impact & Risk Assessment_MPS WEST
- A19_Green Travel Plan_MPS WEST
- A1_SEARs & Mitigation Table_MPS WEST
- A20_Civil Engineer Report incl. WMP_MPS WEST
- A20_MUSIC Model_MPS WEST
- A21_Landscape Design Report_MPS WEST
- A21_Landscape Plans_MPS WEST
- A22_Noise and Vibration Impact Assessment_MPS WEST
- A23_Geotechnical Investigation_MPS WEST
- A24_Social Impact Assessment_MPS WEST
- A25_Survey_MPS WEST
- A26_Traffic and Accessibility Impact Assessment_MPS WEST
- A27_WMP Demolition & Construction_MPS WEST
- A28_B1 WMP Operational_MPS WEST
- A29_B2 WMP Operational_MPS WEST
- A2_Precinct Design Report_MPS WEST
- A30_B3 WMP Operational_MPS WEST
- A31_Design Excellence Strategy_MPS WEST
- A32_Design Competition Report B2 & B3_MPS WEST
- A33_Design Review Report_MPS WEST
- A34_Pedestrian Wind Assessment_MPS WEST
- A35_Preliminary Site Investigation_MPS WEST
- A36_Detailed Site Investigation_MPS WEST
- A37_Interim Audit Advice_MPS WEST
- A38_Statement of Heritage Impact (SoHI)_MPS WEST
- A39_Infrastructure Delivery Management and Staging Plan
- A3_Building B1 Design Report_MPS WEST
- A40_Structural Engineers Report_MPS WEST
- A41_Aviation Report_MPS WEST
- A42_Engagement Report_MPS WEST
- A43_Connecting with Country_MPS WEST
- A44_Construction Management Plan_MPS WEST
- A45_OS4 Amenities Block Drawings_MPS WEST
- A46_Visual Impact Assessment Appendix A_MPS WEST
- A46_Visual Impact Assessment_MPS WEST
- A47_Reflectivity Assessment_MPS WEST
- A48_BCA Compliance Report_MPS WEST
- A49_Accessibility Report_MPS WEST
- A4_Buildings B2 and B3 Design Report_MPS WEST
- A50_Natural Ventilation Design Review_MPS WEST
- A51_Groundwater Seepage Analysis_MPS WEST
- A52_Acid Sulfate Soil Assessment_MPS WEST
- A53_Archaeological Assessment_MPS WEST
- A54_Statutory Compliance Table_MPS WEST
- A55_Affordable Housing Letter_MPS WEST
- A56_Fire Engineering Letter_MPS WEST
- A57_Flood Emergency Response Plan_MPS WEST
- A58_Clause 4.6 Variation to FSR_MPS WEST
- A5_Architectural Drawings_Building B1_MPS WEST
- A6_Architectural Drawings_Building B2_MPS WEST
- A7_Architectural Drawings_Building B3_MPS WEST
- A8_Aboriginal Cultural Heritage Assessment Report_MPS WEST
- A9_Arboricultural Impact Assessment Report_MPS WEST
- Environmental Impact Statement_MPS WEST
Response to Submissions41
- A10_RTS_Landscape Response to Submissions_MPS WEST
- A11_RTS_Statutory Compliance Table_MPS West
- A12_RTS_SEARs Items and Mitigation Measures Table_MPS West
- A13_RTS_VIA_Additional Images_MPS WEST
- A14_RTS_SOHI_MPS WEST
- A15_RTS_Maritime Archaeology Letter_MPS WEST
- A16_RTS_Hydrogeological Report_MPS WEST
- A17_RTS_Natural Ventilation Letter_MPS WEST
- A18_RTS_DRP Minutes_MPS WEST
- A19_RTS_Stormwater Response_MPS WEST
- A1_RTS_Architectural Drawings_B1_MPS WEST
- A1a_RTS_Precinct Summary_MPS WEST
- A20_RTS_Civil Engineering Drawings_MPS WEST
- A21_RTS_Flooding Advice_MPS WEST
- A22_RTS_Ecological Response Summary_MPS WEST
- A23_RTS_BDAR_MPS WEST
- A24_RTS_Biodiversity Management Plan_MPS WEST
- A25_RTS_Vegetation Management Plan_MPS WEST
- A26_RTS_Historical Archaeological Assessment_MPS WEST
- A27_RTS_HARDEM_MPS WEST
- A28_RTS_Heritage Response_SoHI_HAA_MPS WEST
- A29_RTS_Heritage Response_ATR_ACHAR_MPS WEST
- A29a_RTS_Aboriginal Site Recording Form_MPS WEST
- A2_RTS_Landscape Report_B1_MPS WEST
- A30_RTS_Preliminary Hazard Analysis_MPS WEST
- A30a_RTS_PHA Letter_MPS WEST
- A31_RTS_Arborist Report_MPS WEST
- A32_RTS_Traffic Response_MPS WEST
- A33_RTS_Schedule of Unit Compliance_MPS WEST
- A34_RTS_Landscape Plans_MPS WEST
- A35_RTS_Submissions Register_MPS_West
- A36_RTS_Clarification on Job Numbers
- A37_RTS_Response to SES
- A3_RTS_Design Report_B1_MPS WEST
- A4_RTS_Architectural Drawings_B2_MPS WEST
- A5_RTS_Landscape Report_B2_MPS WEST
- A6_RTS_Design Report_B2 and B3_MPS WEST
- A7_RTS_Architectural Drawings_B3_MPS WEST
- A8_RTS_Landscape Report_B3_MPS WEST
- A9_RTS_Open Space Landscape Report_MPS WEST
- Response to Submissions - Melrose Park South-West
Agency Advice19
- CPHR Advice - EIS
- CPHR Advice - RtS
- City of Parramatta Council Interim Submission
- City of Parramatta Council full submission
- DCCEEW Water Advice - EIS
- DCCEEW Water Advice - RtS
- Fisheries Advice - EIS
- Heritage NSW ACH Advice - EIS
- Heritage NSW ACH Advice - RtS
- Heritage NSW Advice - EIS
- Heritage NSW Advice - RtS
- Jemena Advice - EIS
- Parramatta City Council Advice - RtS
- SES Advice - EIS
- SES Advice - RtS
- TfNSW Advice - EIS
- TfNSW Advice - RtS
- Viva Energy Advice - EIS
- Viva Energy Advice - RtS
Additional Information6
Determination7
Management Plans and Strategies2
Other Documents14
- 261138_Reports Distriubtion Statement
- Appointment of Experts
- Approval of Plan Strategy or Study
- Attachment 1 - Post Approval Form_20261009013023
- Attachment 2 - Cover Letter - Condition B4
- Attachment 2 - Excavation Director Nomination
- Attachment 3 - CV_Alexander Beben
- Attachment 3 - GCCV Capability Statement 2026
- Final Arch plans Rev A
- Final Temporary access plan
- Letter of Approval - Condition B4 - Architect
- Letter of approval for staging
- OneDrive_1_22-10-2026
- Staging and Phasing Report MPS WEST A6-A12 (Rev 2)
What's near it
Where it is
- Suburb
- Melrose Park
- Council area
- Parramatta
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.