Where it is in the process

Approved on 18 Nov 2026

  1. SEARs (done)
  2. Prepare EIS (done)
  3. Exhibition (done)
  4. Collate Submissions (done)
  5. Response to Submissions (done)
  6. Assessment (done)
  7. Recommendation (done)
  8. Determination18 Nov 2026 (done)
  9. Approved18 Nov 2026

What it proposes

AI summary. Written from this project's page and its SSD Assessment Report and SSD Instrument of Consent on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it

Out of date. This summary was written from the project's page as it stood on 18 Nov 2026; the page has changed since, so check the stage and documents below.

A nine-storey, 64-apartment building at 138 Maroubra Road

The project is a nine-storey mixed use building at 138 Maroubra Road, Maroubra, in the Randwick City Council area. It would have 64 apartments, 13 of them affordable housing, and one ground floor retail space. The building is up to 32.5 m tall, with 70 car spaces in the retained basement and on level 1. The estimated development cost is $77,600,000. The department expects 40 construction jobs and 10 operational jobs.

The environmental impact statement (EIS) was exhibited from 26 Nov 2025 to 9 Dec 2025. The amended application was exhibited again from 2 Jun 2026 to 15 Jun 2026. The portal records 155 submissions: 151 objecting, 2 supporting and 2 commenting. The department's assessment report of November 2026 recommended approval. A Deputy Secretary of the department, acting for the Minister, approved it on 18 Nov 2026, with conditions. Next, the proponent must meet those conditions before building starts.

Estimated development cost
$77.6MSSD Assessment Report
Apartments
64 apartmentsSSD Instrument of Consent
Affordable housing apartments
13 apartmentsSSD Instrument of Consent
Maximum building height
32.5 mSSD Assessment Report
Car spaces
70 car spacesSSD Instrument of Consent
Construction jobs
40 jobsSSD Assessment Report
Operational jobs
10 jobsSSD Assessment Report
Submissions objecting
151 submissionsPortal page

The department's description

Demolition of existing structures and construction of a mixed used development with in-fill affordable housing.

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0

Submissions

What the public, organisations and public authorities said, counted by where they stood.

155 submissions: 146 from the public, 8 from organisations and 1 from public authorities

Object151
Support2
Comment2

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal

Documents

By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.

78 documents in 10 folders, each on the NSW Planning Portal

Notice of Exhibition1
Early Consultation1
Request for SEARs1
SEARs2
EIS29
Exhibition1
Response to Submissions10
Agency Advice7
Amendments23
Determination3

What's near it

Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project

Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.