Mixed Use Development with In-Fill Affordable Housing - Moseley Street and Donald Street, Carlingford
118 apartments and a childcare centre at Moseley Street, Carlingford
Where it is in the process
Approved on 1 May 2026
What it proposes
AI summary. Written from this project's page and its Assessment Report and Instrument of Consent on the NSW Planning Portal, on 18 Nov 2026. It can be wrong or out of date: check the documents before relying on it. Report a problem with it
118 apartments and a childcare centre at Moseley Street, Carlingford
The project is a mixed-use development at 15A-15B Moseley Street and 25-31 Donald Street, Carlingford, in the City of Parramatta. It has two buildings of 7 to 9 storeys with 118 apartments, of which 23 are affordable housing, plus a childcare centre and three basement levels. The department gives an estimated development cost of $101,819,136, with 159 construction jobs and 15 operational jobs. The site is 5,948 m².
The environmental impact statement (EIS) was exhibited from 9 Oct 2025 to 22 Oct 2025. The department received 9 submissions: 5 objecting, 2 supporting and 2 commenting. The proponent amended the proposal on 23 Feb 2026 and 22 Apr 2026, removing two levels from one building and reducing the apartments. A director of the department, acting for the Minister, approved it on 1 May 2026, with conditions. Next, the proponent must meet those conditions before and during construction.
- Estimated development cost
- $101.8MAssessment Report
- Apartments
- 118 dwellingsAssessment Report
- Affordable housing apartments
- 23 dwellingsAssessment Report
- Construction jobs
- 159 jobsAssessment Report
- Operational jobs
- 15 jobsAssessment Report
- Site area
- 5,948 m²Assessment Report
- Car parking spaces in basement
- 167 car spacesInstrument of Consent
The department's description
Demolition, excavation and construction of two six-storey residential flat buildings (comprising 136 apartments (106 market and 30 affordable housing apartments)) and a 76-place child care centre.
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0
Submissions
What the public, organisations and public authorities said, counted by where they stood.
9 submissions: 7 from the public, 1 from organisations and 1 from public authorities
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: counted by position and by who made them; their text and names stay on the portal
Modifications
1 change to the project after its decision, each assessed as a case of its own, newest first.
Mosley St Carlingford MOD 1 - Building A height increase and facade changesSSD-83870463-Mod-1
Design changes to Building A, including increased heights to Towers A1 and A2, window additions/removals and sill height changes, operable louvres to Level 8 Tower A1 balconies, and driveway gradient changes
Its 9 documents
9 documents in 3 folders, each on the NSW Planning Portal
Notice of Exhibition1
Modification Application7
Agency Advice1
Documents
By folder, as the Planning Portal files them. Each opens the portal's own copy: the proponent's documents are theirs, and Bowerbird keeps none.
107 documents in 10 folders, each on the NSW Planning Portal
Notice of Exhibition1
Request for SEARs1
SEARs2
EIS41
- Appendix A - SEARs Table
- Appendix AA - Social Impact Assessment Carlingford
- Appendix B - Architectural Plans
- Appendix BB - Aboriginal Heritage Assessment
- Appendix C - Statutory Compliance Table
- Appendix CC - Community Housing Provider Letter
- Appendix D - Mitigation Measures
- Appendix DD - Infrastructure Report
- Appendix E - Engagement Summary Table
- Appendix F - Clause 4.6 Variation Request
- Appendix FF - LEC Judgement DA.222.2024
- Appendix G - Engagement Outcomes Report
- Appendix GG - EDC Cost Report
- Appendix H - Design Report
- Appendix HH - Flood Information Certificate
- Appendix I - Stormwater Concept Design
- Appendix II - Public Domain Plans
- Appendix J - Survey Plan
- Appendix JJ - Construction Waste Management Plan
- Appendix K - BCA Report
- Appendix KK - Flood Risk Report
- Appendix L - Access Report
- Appendix LL - Section J Report
- Appendix M - Transport Impact Assessment
- Appendix MM - BASIX Stamped Plans
- Appendix N - Construction Traffic Management Plan
- Appendix O - Noise Impact Assessment
- Appendix P - Integrated Water Management Plan
- Appendix Q - Geotechnical Certificate
- Appendix Q - Geotechnical Report
- Appendix R - Preliminary Site Investigation
- Appendix S - Landscape Plans
- Appendix T - Arborist Report
- Appendix U - ESD Report
- Appendix V - BDAR Waiver Request
- Appendix W - BDAR Waiver
- Appendix X - NatHERS Certificate
- Appendix Y - BASIX Certificate
- Appendix Z - Waste Management Plan
- Application_20250923050240
- Environmental Impact Statement
Response to Submissions25
- Advice from Acoustic consultant Moseley St Carlingford Building
- Amendment Report & Response to Submissions
- Appemdix P - Summary of Design Amendments
- Appendix B - Mitigation Measures
- Appendix C - Updated Statutory Compliance Table
- Appendix D - Clause 4.6 Variation Request (Height)
- Appendix E - Clause 4.6 Variation Request (FSR)
- Appendix F - Amended Architectural Plans
- Appendix G - Amended Design Report
- Appendix H - Amended Landscape Plans
- Appendix I - Addendum Geotechnical Assessment
- Appendix I - Geotechnical Certificate
- Appendix J - Wind Analysis
- Appendix K - Response to Stormwater Matters
- Appendix L - Addendum Traffic Statement
- Appendix M - Addendum Arborist Advice
- Appendix N - BASIX Building Fabric Requirements
- Appendix N - BASIX Stamped Plans
- Appendix N - NatHERS Certificate
- Appendix N - Updated BASIX Certificate
- Appendix O - Substation Design
- Appendix Q - Public Domain Drawings
- Request RTS Letter
- Response to RtS ToA RFI
- Waste Management Plan Application-
Agency Advice5
Amendments18
- Amended Application_20260223031353
- Amended Application_20260422055055
- Amendment Acceptance Letter April
- Amendment Acceptance Letter Feb
- Amendment Report & RtS
- Amendment Report 260422
- Architectural Plans_Part1
- Architectural Plans_Part2
- Architectural Plans_Part3
- Design Report_Part1
- Design Report_Part2
- Design Report_Part3
- Design Report_Part4
- Design Report_Part5
- Design Report_Part6
- FINAL Clause 4.6 Variation Request (FSR)
- FINAL Clause 4.6 Variation Request (Height)
- Final WMP Moseley Street Donald street Carlingford
Additional Information4
What's near it
Where it is
- Suburb
- Carlingford
- Council area
- Parramatta
Source ABS suburbs and localities and local government areas (ASGS 2021), CC BY 4.0
Other State projects near it
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0; straight-line distance
Nearest schools
Source NSW Department of Education, CC BY; straight-line distance
Nearest hospitals
Source AIHW MyHospitals, CC BY 4.0; straight-line distance
Source NSW Planning Portal Major Projects (DPHI), CC BY 4.0: the project's page, read 18 Nov 2026. See it on the map · Every State project
Category and scale: Bowerbird's, from the register's development type and the figures it states, in five levels from minor to regional. Its stage is the portal's on the day it was read.